Skip to the record
The first. The best. The only NoosaWatch™.

Original source · versioned page text

Seaview Terrace Target Program Rev 2 MM

Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                                                                         SEAVIEW TERRACE
                                                                                                                                                  CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                              DRAFT
ID           Task Name                                                  Duration   Start          Finish              July      August September
                                                                                                                                             OctoberNovember
                                                                                                                                                          December
                                                                                                                                                                January February
                                                                                                                                                                               March April   May      June July       August September
                                                                                                                                                                                                                                   OctoberNovember
                                                                                                                                                                                                                                                December
                                                                                                                                                                                                                                                      January February
                                                                                                                                                                                                                                                                     March April                       May       June    July    August September
                                                                                                                                                                                                                                                                                                                                              OctoberNovember
                                                                                                                                                                                                                                                                                                                                                           December
                                                                                                                                                                                                                                                                                                                                                                 January February
                                                                                                                                                                                                                                                                                                                                                                                Ma
                                                                                                                        Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr     May       Jun     Jul     Aug   Sep    Oct   Nov   Dec    Jan    Feb    Mar   Apr                         May        Jun     Jul    Aug    Sep    Oct   Nov   Dec    Jan    Feb
 115                 Reinforce Pool                                     1 wk       Thu 1/06/17    Wed 7/06/17                                                                                            Reinforce Pool
 116                 Services in Pool                                   1 wk       Thu 8/06/17    Wed 14/06/17                                                                                            Services in Pool
 117                 Spray Pool                                         2 days     Thu 15/06/17 Fri 16/06/17                                                                                              Spray Pool
 118               BASEMENT                                             31 days    Mon 3/07/17 Mon 14/08/17                                                                                                                  BASEMENT
 119                 Excavate, Reinforce and Pour Footings              8 days     Mon 3/07/17 Wed 12/07/17                                                                                                      Excavate, Reinforce and Pour Footings
 120                 FRP Ground Slab                                    8 days     Thu 13/07/17 Mon 24/07/17                                                                                                        FRP Ground Slab
 121                 FRP Concrete Walls                                 3 wks      Tue 25/07/17 Mon 14/08/17                                                                                                                 FRP Concrete Walls
 122                 S&I Reinforced Blockwork                           2 wks      Tue 25/07/17 Mon 7/08/17                                                                                                             S&I Reinforced Blockwork
 123               LEVEL 1                                              41 days    Tue 15/08/17 Wed 11/10/17                                                                                                                                LEVEL 1
 124                 Zone 1                                             6 days     Tue 15/08/17 Tue 22/08/17                                                                                                                   Zone 1
 125                     Excavate, Reinforce and Pour Footings          3 days     Tue 15/08/17 Thu 17/08/17                                                                                                                 Excavate, Reinforce and Pour Footings
 126                     FRP Ground Slab                                3 days     Fri 18/08/17   Tue 22/08/17                                                                                                                FRP Ground Slab
 127                 Zone 2                                             32 days    Fri 18/08/17   Tue 3/10/17                                                                                                                             Zone 2
 128                     Formwork to Arches                             2 wks      Fri 18/08/17   Thu 31/08/17                                                                                                                   Formwork to Arches
 129                     Reinforce Arches                               4 days     Fri 1/09/17    Wed 6/09/17                                                                                                                     Reinforce Arches
 130                     Spray Arches                                   1 day      Thu 7/09/17    Thu 7/09/17                                                                                                                     Spray Arches
 131                     Strip Arches                                   2 days     Fri 29/09/17   Tue 3/10/17                                                                                                                             Strip Arches
 132                 Zone 3                                             28 days    Fri 1/09/17    Wed 11/10/17                                                                                                                              Zone 3
 133                     Formwork to Arches                             8 days     Fri 1/09/17    Tue 12/09/17                                                                                                                      Formwork to Arches
 134                     Reinforce Arches                               4 days     Wed 13/09/17 Mon 18/09/17                                                                                                                         Reinforce Arches
 135                     Spray Arches                                   1 day      Tue 19/09/17 Tue 19/09/17                                                                                                                         Spray Arches
 136                     Strip Arches                                   1 day      Wed 11/10/17 Wed 11/10/17                                                                                                                                Strip Arches
 137                 Zone 4                                             7 days     Wed 20/09/17 Thu 28/09/17                                                                                                                             Zone 4
 138                     Excavate, Reinforce and Pour Footings          4 days     Wed 20/09/17 Mon 25/09/17                                                                                                                            Excavate, Reinforce and Pour Footings
 139                     FRP Ground Slab                                3 days     Tue 26/09/17 Thu 28/09/17                                                                                                                            FRP Ground Slab
 140               LEVEL 1                                              20 days    Fri 29/09/17   Fri 27/10/17                                                                                                                                    LEVEL 1
 141                 Form, Reinforce, Pour Concrete Walls               3 wks      Fri 29/09/17   Fri 20/10/17                                                                                                                                Form, Reinforce, Pour Concrete Walls
 142                 Reinforced Concrete Block Walls                    2 wks      Mon 16/10/17 Fri 27/10/17                                                                                                                                      Reinforced Concrete Block Walls
 143               LEVEL 2                                              61 days    Mon 30/10/17 Tue 13/02/18                                                                                                                                                                       LEVEL 2
 144                 ZONE 1                                             29 days    Mon 30/10/17 Thu 7/12/17                                                                                                                                                   ZONE 1
 145                     Form Suspended Slab and Beams                  6 days     Mon 30/10/17 Mon 6/11/17                                                                                                                                         Form Suspended Slab and Beams
 146                     Reinforce Suspended Slab                       4 days     Tue 7/11/17    Fri 10/11/17                                                                                                                                         Reinforce Suspended Slab
 147                     Pour Suspended Slab                            1 day      Mon 13/11/17 Mon 13/11/17                                                                                                                                           Pour Suspended Slab
 148                     Strip Suspended Slab                           3 days     Tue 5/12/17    Thu 7/12/17                                                                                                                                                 Strip Suspended Slab
 149                 ZONE 2                                             29 days    Tue 7/11/17    Fri 15/12/17                                                                                                                                                  ZONE 2
 150                     Form Suspended Slab and Beams                  6 days     Tue 7/11/17    Tue 14/11/17                                                                                                                                         Form Suspended Slab and Beams
 151                     Reinforce Suspended Slab                       4 days     Wed 15/11/17 Mon 20/11/17                                                                                                                                             Reinforce Suspended Slab
 152                     Pour Suspended Slab                            1 day      Tue 21/11/17 Tue 21/11/17                                                                                                                                             Pour Suspended Slab
 153                     Strip Suspended Slab                           3 days     Wed 13/12/17 Fri 15/12/17                                                                                                                                                   Strip Suspended Slab
 154                 ZONE 3                                             30 days    Wed 15/11/17 Tue 16/01/18                                                                                                                                                              ZONE 3
 155                     Form Arches                                    2 wks      Wed 15/11/17 Tue 28/11/17                                                                                                                                                Form Arches
 156                     Reinforce Arches                               5 days     Wed 29/11/17 Tue 5/12/17                                                                                                                                                  Reinforce Arches
 157                     Spray Arches                                   1 day      Wed 6/12/17 Wed 6/12/17                                                                                                                                                   Spray Arches
 158                     Strip Arches                                   2 days     Mon 15/01/18 Tue 16/01/18                                                                                                                                                              Strip Arches
 159                 ZONE 4                                             20 days    Wed 29/11/17 Tue 16/01/18                                                                                                                                                              ZONE 4
 160                     Form Arches                                    8 days     Wed 29/11/17 Fri 8/12/17                                                                                                                                                   Form Arches
 161                     Reinforce Arches                               4 days     Mon 11/12/17 Thu 14/12/17                                                                                                                                                   Reinforce Arches
 162                     Spray Arches                                   1 day      Fri 15/12/17   Fri 15/12/17                                                                                                                                                 Spray Arches
 163                     Strip Arches                                   2 days     Mon 15/01/18 Tue 16/01/18                                                                                                                                                              Strip Arches
 164                 ZONE 5                                             31 days    Mon 11/12/17 Tue 13/02/18                                                                                                                                                                       ZONE 5
 165                     Form Arches                                    2 wks      Mon 11/12/17 Fri 22/12/17                                                                                                                                                     Form Arches
 166                     Reinforce Arches                               4 days     Mon 15/01/18 Thu 18/01/18                                                                                                                                                              Reinforce Arches
 167                     Spray Arches                                   1 day      Fri 19/01/18   Fri 19/01/18                                                                                                                                                            Spray Arches
 168                     Strip Arches                                   2 days     Mon 12/02/18 Tue 13/02/18                                                                                                                                                                     Strip Arches
 169               LEVEL 2                                              15 days    Mon 15/01/18 Mon 5/02/18                                                                                                                                                                     LEVEL 2
 170                 FRP Walls                                          3 wks      Mon 15/01/18 Mon 5/02/18                                                                                                                                                                    FRP Walls
 171               ROOF                                                 39 days    Tue 6/02/18    Tue 3/04/18                                                                                                                                                                                   ROOF


                                   Task                          Summary                                   External Milestone                         Inactive Summary                       Manual Summary Rollup                          Finish-only                                         Critical Split
Project: Seaview Terrace Program
                                   Split                         Project Summary                           Inactive Task                              Manual Task                            Manual Summary                                 Deadline                                            Progress
Date: Fri 5/08/16
                                   Milestone                     External Tasks                            Inactive Milestone                         Duration-only                          Start-only                                     Critical

                                                                                                                                                                         Page 3
Log in to download the original file

Seaview Terrace Target Program Rev 2 MM.pdf · 654 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.