Seaview Terrace Target Program Rev 2 MM
Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.
SEAVIEW TERRACE
CONSTRUCTION PROGRAM - TARGET
DRAFT
ID Task Name Duration Start Finish July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
Ma
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
115 Reinforce Pool 1 wk Thu 1/06/17 Wed 7/06/17 Reinforce Pool
116 Services in Pool 1 wk Thu 8/06/17 Wed 14/06/17 Services in Pool
117 Spray Pool 2 days Thu 15/06/17 Fri 16/06/17 Spray Pool
118 BASEMENT 31 days Mon 3/07/17 Mon 14/08/17 BASEMENT
119 Excavate, Reinforce and Pour Footings 8 days Mon 3/07/17 Wed 12/07/17 Excavate, Reinforce and Pour Footings
120 FRP Ground Slab 8 days Thu 13/07/17 Mon 24/07/17 FRP Ground Slab
121 FRP Concrete Walls 3 wks Tue 25/07/17 Mon 14/08/17 FRP Concrete Walls
122 S&I Reinforced Blockwork 2 wks Tue 25/07/17 Mon 7/08/17 S&I Reinforced Blockwork
123 LEVEL 1 41 days Tue 15/08/17 Wed 11/10/17 LEVEL 1
124 Zone 1 6 days Tue 15/08/17 Tue 22/08/17 Zone 1
125 Excavate, Reinforce and Pour Footings 3 days Tue 15/08/17 Thu 17/08/17 Excavate, Reinforce and Pour Footings
126 FRP Ground Slab 3 days Fri 18/08/17 Tue 22/08/17 FRP Ground Slab
127 Zone 2 32 days Fri 18/08/17 Tue 3/10/17 Zone 2
128 Formwork to Arches 2 wks Fri 18/08/17 Thu 31/08/17 Formwork to Arches
129 Reinforce Arches 4 days Fri 1/09/17 Wed 6/09/17 Reinforce Arches
130 Spray Arches 1 day Thu 7/09/17 Thu 7/09/17 Spray Arches
131 Strip Arches 2 days Fri 29/09/17 Tue 3/10/17 Strip Arches
132 Zone 3 28 days Fri 1/09/17 Wed 11/10/17 Zone 3
133 Formwork to Arches 8 days Fri 1/09/17 Tue 12/09/17 Formwork to Arches
134 Reinforce Arches 4 days Wed 13/09/17 Mon 18/09/17 Reinforce Arches
135 Spray Arches 1 day Tue 19/09/17 Tue 19/09/17 Spray Arches
136 Strip Arches 1 day Wed 11/10/17 Wed 11/10/17 Strip Arches
137 Zone 4 7 days Wed 20/09/17 Thu 28/09/17 Zone 4
138 Excavate, Reinforce and Pour Footings 4 days Wed 20/09/17 Mon 25/09/17 Excavate, Reinforce and Pour Footings
139 FRP Ground Slab 3 days Tue 26/09/17 Thu 28/09/17 FRP Ground Slab
140 LEVEL 1 20 days Fri 29/09/17 Fri 27/10/17 LEVEL 1
141 Form, Reinforce, Pour Concrete Walls 3 wks Fri 29/09/17 Fri 20/10/17 Form, Reinforce, Pour Concrete Walls
142 Reinforced Concrete Block Walls 2 wks Mon 16/10/17 Fri 27/10/17 Reinforced Concrete Block Walls
143 LEVEL 2 61 days Mon 30/10/17 Tue 13/02/18 LEVEL 2
144 ZONE 1 29 days Mon 30/10/17 Thu 7/12/17 ZONE 1
145 Form Suspended Slab and Beams 6 days Mon 30/10/17 Mon 6/11/17 Form Suspended Slab and Beams
146 Reinforce Suspended Slab 4 days Tue 7/11/17 Fri 10/11/17 Reinforce Suspended Slab
147 Pour Suspended Slab 1 day Mon 13/11/17 Mon 13/11/17 Pour Suspended Slab
148 Strip Suspended Slab 3 days Tue 5/12/17 Thu 7/12/17 Strip Suspended Slab
149 ZONE 2 29 days Tue 7/11/17 Fri 15/12/17 ZONE 2
150 Form Suspended Slab and Beams 6 days Tue 7/11/17 Tue 14/11/17 Form Suspended Slab and Beams
151 Reinforce Suspended Slab 4 days Wed 15/11/17 Mon 20/11/17 Reinforce Suspended Slab
152 Pour Suspended Slab 1 day Tue 21/11/17 Tue 21/11/17 Pour Suspended Slab
153 Strip Suspended Slab 3 days Wed 13/12/17 Fri 15/12/17 Strip Suspended Slab
154 ZONE 3 30 days Wed 15/11/17 Tue 16/01/18 ZONE 3
155 Form Arches 2 wks Wed 15/11/17 Tue 28/11/17 Form Arches
156 Reinforce Arches 5 days Wed 29/11/17 Tue 5/12/17 Reinforce Arches
157 Spray Arches 1 day Wed 6/12/17 Wed 6/12/17 Spray Arches
158 Strip Arches 2 days Mon 15/01/18 Tue 16/01/18 Strip Arches
159 ZONE 4 20 days Wed 29/11/17 Tue 16/01/18 ZONE 4
160 Form Arches 8 days Wed 29/11/17 Fri 8/12/17 Form Arches
161 Reinforce Arches 4 days Mon 11/12/17 Thu 14/12/17 Reinforce Arches
162 Spray Arches 1 day Fri 15/12/17 Fri 15/12/17 Spray Arches
163 Strip Arches 2 days Mon 15/01/18 Tue 16/01/18 Strip Arches
164 ZONE 5 31 days Mon 11/12/17 Tue 13/02/18 ZONE 5
165 Form Arches 2 wks Mon 11/12/17 Fri 22/12/17 Form Arches
166 Reinforce Arches 4 days Mon 15/01/18 Thu 18/01/18 Reinforce Arches
167 Spray Arches 1 day Fri 19/01/18 Fri 19/01/18 Spray Arches
168 Strip Arches 2 days Mon 12/02/18 Tue 13/02/18 Strip Arches
169 LEVEL 2 15 days Mon 15/01/18 Mon 5/02/18 LEVEL 2
170 FRP Walls 3 wks Mon 15/01/18 Mon 5/02/18 FRP Walls
171 ROOF 39 days Tue 6/02/18 Tue 3/04/18 ROOF
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Critical Split
Project: Seaview Terrace Program
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Fri 5/08/16
Milestone External Tasks Inactive Milestone Duration-only Start-only Critical
Page 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.