Original source · versioned page text
MCU16/0079 Town Planning Report
Town Planning Report
“Undefined Use”
Staged Extension & Refurbishment of Existing RSL Club
5 Memorial Ave, Tewantin QLD 4565
Lot 3 on T16319 and Lot 10 on SP273411
Environmental Protection S10.1 Roads and stormwater drainage follow the edge of Complies with the Probable Solution – The proposed
O10 Roads and stormwater drainage infrastructure are existing disturbed areas, roads and stormwater drainage has been designed to ensure
located and aligned so as to— a) minimise disturbance to native vegetation and/or other minimal disturbance to native vegetation and habitat areas.
a) minimise disturbance to native vegetation and/or other habitat areas; All stormwater drainage will be collected on site and treater
habitat areas; b) protect and maintain wildlife corridor movements and the prior to its discharge. It is considered the design and
b) protect and maintain wildlife corridor movements and the safety of native fauna; treatment of the stormwater infrastructure will protect and
safety of native fauna; c) minimise changes to the hydrological regime, including maintain wildlife corridors within the vicinity of the site.
c) minimise changes to the hydrological regime, including drainage patterns, run-off and water quality;
drainage patterns, run-off and water quality; d) avoid crossing watercourses, drainage lines and wetlands, The development does not include any watercourse or
d) avoid crossing watercourses, drainage lines and wetlands, but where such crossings are unavoidable, disturbed drainage line crossings, and where possible earthworks have
but where such crossings are unavoidable, disturbed areas are reinstated and revegetated on completion of been minimised. Council is directed to Appendix D – Sewer
areas are reinstated and revegetated on completion of works; and & Stormwater Plans for further details.
works; and e) minimise bulk earthworks.
e) minimise bulk earthworks.
O11 Roads and stormwater drainage infrastructure is proven No solution provided Complies with the Specific Outcome – The proposed roads
to be suitable for its use prior to Council accepting the and stormwater drainage infrastructure has been designed of
dedicated asset. an adequate size to cater for the maximum potential runoff
capacity. Council is directed to Appendix D – Sewer and
Stormwater Plans for further details.
O12 Alignment of stormwater drainage infrastructure is to S12.1 The location, design and construction of stormwater Complies with the Probable Solutions – The proposed
allow for easy access for the ongoing maintenance by drainage structures is in accordance with Sections 4 and 5 of location and design of the stormwater drainage has been
Council. PSP5, Engineering Design Standards - Roads, Drainage and completed in accordance with PSP5. In this instance no
Earthworks; AND additional easements are required. Council is directed to
S12.2 Where infrastructure is located on private land an Appendix D – Architectural Plans for further details.
easement is dedicated over the infrastructure in accordance
with Section 4 of PSP 5, Engineering Design Standards –
Roads, Drainage and Earthworks.
14.148 Frontage works
O13 Development is provided with external roadworks along S13.1 The following infrastructure components already exist Complies with the Probable Solutions – The proposed
the full extent of the frontage of the site to an appropriate at the frontage of the site or are provided at the developer’s development incorporates all infrastructure as noted with this
standard having regard to the specified function of the road. expense— code. The proposed development will maintain the provided
a) full width sealed road; infrastructure which is already provided to the site. The use of
b) concrete kerb and channel where appropriate; consolidating the crossovers will include upgrades to the kerb
July 2016 Page | 50
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (MCU16_0079 Town Planning Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.