PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 25 MARCH 2014
(iii) Section 3.6.4 and Figure 3A shall be revised to be consistent in terms of benching
levels. The initial development phase shall be in accordance with the footprint
identified in Figure 3A. Figure 3A to be changed from “Conceptual Short Term Quarry
Development Plan” to “Short Term Works Development Plan”;
(iv) the initial development phase to be limited to 7 years as identified in the amended Kin
Kin Quarry Management Plan or by reaching the limits of extraction as outlined in
Figure 3A or whichever is the sooner;
(c) advise Neilsen’s Quality Gravels Pty Ltd that the amended Kin Kin Quarry Management
Plan must be updated to the reasonable satisfaction of Council before further quarrying
stages commence, as storm water management is not adequately addressed for
subsequent stages;
(d) request the Chief Executive Officer to seek confirmation from the Department of
Environment and Heritage Protection that they are prepared to enforce storm water
management provisions that prevent overtopping of the Detention Basin, and other
significant direct impacts on the Noosa River Catchment on the understanding that the
Noosa River currently enjoys the highest health rating of any South East Queensland river
system, is an integral feature of the Noosa Biosphere Reserve, as well as the Cooloola
Section of the Great Sandy National Park.
Ordinary Meeting – 23 May 2013 (Council Resolution OM13/80)
ITEM 7.1.1 KIN KIN QUARRY AMENDED QUARRY MANAGEMENT PLAN
That Council:
(a) receive and note the report titled 'Kin Kin Quarry - Amended Quarry Management Plan' and
(b) approve the updated Kin Kin Quarry Management Plan at Appendix A, prepared by
Groundwork Plus and dated February 2013, for the initial quarry development phase only,
subject to the amendments contained in Appendix B and the following amendments:
(i) 14. Section 2.7 and the Road Transport Protocol must be revised to specify that the
approved primary haul route is Pomona Kin Kin Road, with the local road network
permitted only for local deliveries where a local road is the only access route to a
delivery site. Use of local roads is not to occur as an alternative to Pomona Kin Kin
Road for the purpose of shortening trip distances or convenience; and
(ii) Section 3.6.8 shall be amended to state that detailed Erosion and Sediment Control
plans are to be submitted prior to any works commencing in an area beyond those
shown in Figure 3A - Short Term Quarry Extent.
(c) delegate authority to the Chief Executive Officer to write to appropriate authorities within
the Department of Environment & Heritage Protection requesting a stringent review of the
ERA conditions imposed on the Kin Kin Quarry, particularly with respect to the retention
dam, diversion drains, and release of contaminated water, on the understanding that
(i) over the past four years, since April 2009, according to Council's hydrologists,
measured rainfall in the Kin Kin Catchment has resulted in 7 rainfall events that
exceeded a 1-in-5 probability, thus the capacity of the sediment basins and
stormwater management may need to be reviewed, and
(ii) the Wahpunga Creek into which contaminated material will flow is a tributary of the
Noosa River System, which resides in the Noosa Biosphere Reserve, flows into the
Cooloola section of the Great Sandy National Park, and currently enjoys the highest
Healthy Waterway Ecosystem Health Monitoring Program rating of any river in South
East Queensland, and
Page 24 of 231
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.