Driited Pier Reinforcement:
                             Pier Depth mm                           Slab Piers
                               up to 1500
                               1500-2500          2xN12bars
                               2500-4000          4xN12bars          2xN12bars
                               4000-6000          6xN12 bars         4xN12bars

     Floor Slab Details:
.    We recommend reinforcing the floor slab as shown with SL82 slab fabric and the thickenings as
     specified.
     Where the foundation level of these thickenings is below prepared pad level, it may be advantageous to
     excavate them at the same time as the perimeter footing.
     Where the beams intersect the perimeter footing, their base must be graded down to the footing base
     level, 3 x N12 bars must be cogged into the footing, and lapped 500 with the beams trench mesh. Refer
     to the attached details.
     A levelling layer under the floor slab is to comprise of granular material compacted in 150mm layers.
     Either well graded sand or crusher dust can be used.
     An approved polyethylene damp proof membrane of 0.2mm (min.) thickness is to be placed over the
     levelling layer. Laps are to be a minimum of 200mm and be taped. All service penetrations and punctures
     are to be fully taped. The membrane is to be extended down the inside face of the perimeter footings.
     Where rock is encountered within the slab area and encroaches within the slab depth it should be
     excavated to a level which enables placement of a 100mm (min.) layer of granular material under the
     slab.
     Notes:
     All building dimensions are to be obtained from the approved pians. The builder must ensure that the final
     pier placement meets all the requirements of this report (both written specifications and cross-sections).
     All excavations must be totally free of all loose material and debris before pouring. They must be cleaned
     out so that the concrete is poured onto undisturbed ground. Tamping and/or watering loose material is
     not acceptable.
     We strongly recommend footing excavations be inspected by a qualified person with appropriate
     experience to confirm the founding material and level is as nominated herein.
      Similarly all preparations should be inspected prior to the pouring of concrete by a qualified
      person with appropriate experience to confirm that the workmanship and construction conforms
      with the details and recommendations contained herein.
      Tiled Areas:
      In areas where ceramic floor tiles or brittle coverings alike are required we recommend increasing the
      size of the slab mesh by one grade. Use flexible adhesives when affixing tiles and delay the laying for as
      long as possible (at least 3 months, preferably 6 months) after the slab is poured.

      $CG CONSULTING ENGINEERS                         4                                  SCG Ref: 16078(S)

Used in these records

About this file

File size
702 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015CE08.001.pdf · 702 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.