SPECIAL MEETING AGENDA 16 DECEMBER 2019
Portion 2 (Thomas Street Site)
Reconstruction of existing reinforced concrete RCBCs at the Thomas Street intersection, as
indicated in Figure 1 below.
Portion includes new pedestrian refuge and crossing opportunity at the western roundabout
approach and associated works.
Portion 3 (The Cockleshell Site)
Reconstruction of existing reinforced concrete RCBCs at The Cockleshell intersection as
indicated in Figure 1.
Portion includes pedestrian crossing improvements to the existing raised pedestrian crossing
to the east of The Cockleshell intersection and associated works.
Portion 4 (Robert Street Site)
Reconstruction of existing reinforced concrete RCBCs at the Robert Street intersection as
indicated by Figure 1.
Portion includes new raised pedestrian crossing to the east of Robert Street, improvements to
the existing pedestrian crossing to the west of Robert Street and associated works and
necessary water main lowering works.
Portion 5 (Corridor Renewal)
Profiling and asphalt resurfacing of road corridor between Cloudsley Street and Albert Street
as indicated by Figure 2, provision of on-street bicycle lanes and minor line marking and on-
street parking alterations.
Figure 1 - Stormwater Renewal Sites
Figure 2 - Corridor Renewal Extent of Works
Page 13 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.