SPECIAL MEETING AGENDA 16 DECEMBER 2019
9. Risks & Opportunities
RISKS MITIGATION
Finance
Council request for scope increases. This is to be mitigated through the Capital Works Project
Control Group and Capital Works Executive management
and limitation of client requested scope variations.
Scope changes once construction Council acceptance of scope as awarded with intention of
commences and project becomes publically not increasing scope.
visible.
Geotechnical conditions give rise for Previous geotechnical investigations have been
contractor claiming variation costs. considered and allowance for adverse latent conditions is
included in the contingency.
Contractor claims for variations based on As above, this has been mitigated through the lump sum
costs for environmental impact mitigation procurement method.
exceeds allowances.
Clashes with underground services give rise All known underground services have been located, and
for contractor claiming variation costs. necessary relocation included in scope of works. Scope
has been limited to placement of new infrastructure within
existing infrastructure envelopes.
Contingency amount being insufficient This risk may be mitigated through the adoption of further
value engineering to occur during the construction phase
process.
Program
There is the potential that the project is The contractor is required to include “wet weather”
delayed due to wet weather allowances into their schedule.
Construction takes longer due to site being In the event of delays the contractor is able to mobilise
more constrained than allowed. additional equipment at no additional cost to bring program
on track.
Resource risk Hall Contracting have nominated a capable team and
combining two work fronts at one time reduces the
resourcing risks to this project. The appointment of an
internal superintendent mitigates the resourcing risk for
Council.
Safety
This is a high risk project due to proximity to Prior to construction commencing, work place health and
traffic and pedestrians. safety and pedestrian and traffic management plans will be
required to be submitted to Council for review. Regular
audits on contractor compliance with these approved plans
will be undertaken by Council throughout construction.
Environmental Harm
There is risk that the works do impact on Council has engaged an independent arborist to ensure
existing mature vegetation. that mature trees are protected and the construction
methodology to ensure impacts are minimised
Risk of spills from materials. Contractors are required to have an environment
management plan which will be reviewed and approved by
Council prior to commencement.
Sediment and erosion control Contractor is required to prepare and implement a certified
Erosion and Sediment Control Plan. Works methodology
will be applied that minimises the duration/extent of
exposed areas.
Scope and Quality
Risk of not meeting project objectives To be managed through Council staff ensuring the original
design and specifications are met.
Page 16 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.