GENERAL COMMITTEE MEETING MINUTES 16 NOVEMBER 2020
Car Parking
41. Carparking shall be provided within the sites generally as shown on
drawings numbered DA_114 “Masterplan/Carpark Layout” Rev. 3 prepared
by Thomson Adsett Architects dated 15 October 2020 and DA_133
“Apartment Buildings – Basement” prepared by Smith and Tracey
Architects dated November 2018 and within the “Independent Living Units”
as shown the approved floor plans, except as modified herein.
Storm Water Quality
81. Any proprietary stormwater quality improvement device included to achieve
the required stormwater quality Management Objectives specified in
Section 4 of the Girraween Stormwater Management Plan, must
demonstrate only be granted an Operational Works Approval on the
following provisions:
a. A suitably qualified and experienced professional must provide
independent verification that the parameters within the node for the
device in MUSIC modelling have been tested and verified as per
Stormwater Australia (2018) Stormwater Quality Improvement
Device Evaluation Protocol. Version 1.2 December 2018 to achieve
the predicted outcomes in the MUSIC model for the development.
For the purpose of this condition, the suitably qualified and
experienced professional must be able to demonstrate a minimum 10
years urban stormwater testing and modelling experience and be
verified in writing by Stormwater Australia as having an appropriate
reputation and track record within the stormwater industry to provide
such independent advice.
b. Where testing to achieve the certification of the proprietary
stormwater quality improvement device is from an area with rainfall
intensities and patterns that are statistically inconsistent with the
region of the Noosa Shire that the device is to be installed, and / or
the size of the development the device has been tested on is more
than 2500m2 smaller than the development the device is proposed
to service, the following additional conditions apply:
i. The proprietary stormwater device treatment train must be
tested and re-verified in accordance with the Stormwater
Australia (2018) Stormwater Quality Improvement Device
Evaluation Protocol. Version 1.2 December 2018. A suitably
qualified and experienced professional, as verified by
Stormwater Australia must use the results from the onsite
testing to re-run the MUSIC node for the proprietary devices
and confirm whether or not the required pollutant reduction
efficiencies of 80% reduction in Total Suspended Solids, 60%
reduction in Total Phosphorous and 45% reduction in Total
Nitrogen for the overall development are delivered.
Page 8 of 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.