(ii) Constructed such that it is immune from flooding during a peak 10
year ARI event and has maximum depth of inundation of 250 mm
and DV < 0.6 during a peak 100 year ARI flood event. Crossings
shall be constructed such that there are no offsite flood impacts on
land not owned by Council. Further, the road crossings shall be
constructed such that they do not change the standing water level
within the land upstream of the road;
(iii) Aligned generally along the centreline of the existing track and varied
where necessary to preserve existing significant vegetation;
(iv) Remove the temporary turnaround area adjacent to Lot 9;
(v) A temporary turnaround facility must be constructed adjacent to the
eastern boundary of Lot 49. The temporary turnaround facility must
be in accordance with an Operational Works approval and must be of
sufficient size to accommodate the 3-point turn manoeuvre of a
Waste Collection Vehicle (WCV);
(vi) Intersections with the proposed internal road; and
(vii) Installation of street lighting at the intersections and elsewhere as
required.
These works must be completed prior to the sealing of the Survey Plan for
Stage 2.
(c) Stage 4 - that part of Hollett Road extending from the cul-de-sac turnaround
area adjacent to Lot 49 to the eastern side of the Walter Hay Drive culvert
shall be:
(i) Designed and constructed with a 4 metre wide sealed surface on a 4
metre wide formation;
(ii) Include a single passing bay on the eastern side of Walter Hay Drive
underpass and a “Give Way” sign, and elsewhere where site lines
are obstructed;
(iii) That part of Hollett Road extending from the eastern side of the
culvert for Walter Hay Drive to the existing access track within Lot 52
shall be designed and constructed with a 4 metre wide gravel surface
formation; and
(iv) The temporary turnaround adjacent to the eastern boundary of Lot 49
must be sealed.
19. A new intersection with Hollett Road must be constructed at a point approximately
100 metres from Eumundi-Noosa Road, and joining the new formation of Hollett Road
(required by condition 16) to the existing formation. The works must be undertaken
in accordance with an Operational Works approval and must include in particular:
(a) vehicle priority maintained east/west along the existing Hollett Road;
(b) provision of sight distances adequate for the design speed of the road;
(c) Street signage and line-marking; and
(d) Street lighting with the number of street lights and their location to be
determined at operational works stage.
These works must be completed prior to the sealing of the Survey Plan for Stage 1.
Site Access and Driveways
20. A sealed access driveway must be provided for all lots with a swale/bioretention
swale drain located in their frontage, if applicable. The access driveway must extend
from the edge of the road formation to the property boundary. The works must be
undertaken in accordance with an Operational Works approval and must include in
4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.