Part 6 of 37 Appendix 3 - Geotechnical Assessment MCU12/0208
Very large file (49.3 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Noosa on Weyba
freedraining fill should be compacted to a minimum dry density ratio of 80% standard compaction.
Compaction should be achieved by using a static smooth roller drum not less than 10 tonne in static weight.
Compaction of fill is required for a number of reasons:-
. Fill should be compacted to the degree that significant settlement within the fill will not occur.
. Compaction of each layer is required sufficient to provide suitable working surface for
subsequent fill lifts and to enable compaction to be carried out on subsequent lifts.
It is recommended that the placement of all structural fill be inspected and tested by Cardno Bowler to a level
1 requirement during the earthworks operations to ensure that all fill is placed in a ’controlled manner’, in
accordance with AS3798-2007 ’Guidelines on Earthworks for Commercial and Residential Developments’.
The near surface silty sand encountered on the site may be particularly difficult to work and compact,
especially if it becomes wet. The material has relatively good engineering properties if it is compacted in
place to the required density and confined by overlying layers. However, if the moisture content is too high
at the time of site preparation work, it may become spongy and may heave under the load of construction
equipment, can be difficult to traffic and compact, and may slow to drain and dry out.
Traffickability
During this investigation, access around the natural areas of the site was quite difficult due to the soft and
clayey nature of near surface soil with ponding water.
If at any stage there is a need for a haul road to be developed, the following construction method is
recommended:
. Strip the grass and organic root zone and allow the surface to dry to promote some surface
crust
.
Following stripping and drying, place a minimum thickness of 500mm to 600mm of granular
material of a maximum particle size of 75mm over the stripped surface.
. After the initial lift, subsequent lifts, preferably with granular material, can be placed and
compacted in the conventional way.
5.2 Building Footings
Based on the classification test results, the estimated surface movement of the existing soil profile due to
seasonal variations in moisture content varies across the site to between 25mm to 65mm. This indicates
that the classification of site areas may vary between Class ’M’, Class ’H1’ and Class ’H2’ in accordance with
AS2870-2011 ’Residential Slabs and Footings’ on the basis of shrink/swell potential.
However, due to the depths of soft and firm clays and very loose to loose sands across the site, the site must
be reclassified as Class ’P’ in accordance with AS2870-2011.
More localised, site specific boreholes will be required in the future to confirm the classification for structures
in a particular area or location.
Based on the nature of the proposed development and the subsurface conditions encountered, it is
suggested that either high or deep level footings may be adopted dependent on the type of structure to be
constructed.
Prepared for Cardno (Old) Page 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 6 of 37 Appendix 3 - Geotechnical Assessment MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 49.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.