The parameters shown in Table 6 may be used for footing design purposes. However, if bored piles are
adopted, the base of the piles must be inspected during construction to ensure that material of adequate
capacity supports each pile.
Table 6: Bearing Capacities for Bored Piles
Material Type Design Equivalent Design Equivalent
FILL
I Skin Friction
$gfs
(kPa)
NR
I Base Bearing Capacity
$gfb
(kPa)
NR
NATURAL- Loose Sand 3 NR
NATURAL -
Medium Dense Sand 5 150
NATURAL- Soft to Firm Clay NR NR
NATURAL -
Stiff Clay 17 150
NATURAL -
Very Stiff or Better Clay 20 300
XW, MUDSTONE 60 1000
Notes:
a) NR = Not Recommended
b) Ignore top 1.5m of profile in pile capacity calculations.
c) The above values were compiled assuming that the pile depth will be at least 5 times that of its pile
diameter.
d) A geotechnical strength reduction factor (<pg) of 0.4 has been applied to the ultimate parameters in the
calculation of the above design equivalent capacities.
The advantage of the alternative deep level footing types (driven timber piles, push piles, screw in steel
piles) is that they can be installed under a performance specification and they can be installed when there is
a high water table or where drilled shafts would collapse without support.
Articulation
It is recommended that the external brickwork walls be articulated by the use of full height (footings to eaves)
openings or vertical construction joints at a maximum spacing of 6.0 metres to prevent cracking of brickwork
caused by possible differential movement of the foundations. This articulation can be achieved by using full
height doors or windows or using flexible cladding over or under them. Construction joints may be hidden by
down pipes. Reference should be made to the Cement & Concrete Association of Australian publication
’Articulated Walling’ Construction Note TN61 for further information regarding articulation.
Maintenance
The importance of avoiding leakage from underground services and drains near the buildings is stressed.
Any leaking services or blocked drains should be remedied promptly. For
highly expansive clays it is
advisable to use flexible joints allowing horizontal and vertical movement where service pipes pass through
the foundation structure (floor and slab).
Future shrubs and trees should be placed at a distance at least equivalent to their mature height away from
the building for Class ’M’ sites, 1.5 times their mature height for Class ’H1’ and ’H2’ sites to minimise the
potential for the moisture demand causing shrinkage movement in expansive founding soils. Existing trees
in the proposed building area can also cause movement in expansive soil when removed. It is advisable to
remove such trees at least 3 months prior to construction.
Prepared for Cardno (Old) Page 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 6 of 37 Appendix 3 - Geotechnical Assessment MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 49.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.