Early Referral Agency Response - Planning RAP25 0030 (As Published) · RAP25/0030

of 6

Text shows just the words. Original shows the document exactly as it was published.

                        Stormwater Drainage
                 13.    The site must be provided with a stormwater drainage system connecting to a lawful
                        point of discharge. Stormwater runoff from the development must be disposed of either
                        on-site or discharged to Bayview Road. Stormwater runoff must be disposed of and or
                        discharged without causing scour or damage to the subject site or any adjoining
                        property.
                        Geotechnical Stability
                 14.    All works must be carried out in accordance with the recommendations of a site specific
                        Geotechnical Report prepared by a qualified person* and endorsed through a building
                        approval.
                        *(Refer to Advisory Note)
                 15.    At the completion of the development works certification must be submitted to Council
                        from a qualified person* which certifies that the development has been constructed in
                        accordance with the recommendations contained in the site specific Geotechnical
                        Report and that the development has a minimum factor of safety against landslip of 1.5
                        in the long term.
                        *(Refer to advisory Note)
                        Earthworks and Retaining Walls
                 16.    All earthworks and associated batters/retaining structures, both above and below ground
                        level, both temporary and permanent, must be contained entirely within the subject site
                        unless written permission from the respective landowner(s) is provided to Council. All
                        earthworks must be undertaken in accordance with the provisions of Australian Standard
                        AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
                        Damage to Services and Assets
                 17.    Any damage caused to existing services and assets as a result of the development
                        works must be repaired at no cost to the asset owner at the following times:
                            a.         where the damage would cause a hazard to pedestrian or vehicle safety,
                                       immediately; or
                            b.         where otherwise, upon completion of the works associated with the
                                       development.
                        Any repair work which proposes to alter the alignment or level of existing services and
                        assets must first be referred to the relevant service authority for approval.
                 1.     REFERENCE DOCUMENTS

                  Doc No.         Rev.       Document Name                                            Date

                  -               S24-       Stormwater Management Report prepared by Westera 17 April 2025
                                  198        Partners Pty Ltd

                  -               PG-        Preliminary Geotechnical Investigation and Slope Stability December
                                  12709      Assessment prepared by Pacific Geotech Consulting 2024
                                             Geotechnical Engineers

                  A0.106          7          Demolition Site Plan prepared by Myers Architecture      26.02.2026




                                                                                                        Page 4 of 6
Document Set ID: 24605219
Version: 3, Version Date: 17/03/2026

Used in these records

About this file

File size
113 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Early Referral Agency Response - Planning RAP25 0030 (As Published).pdf · 113 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.