June 2006 -9- 06683025-1000(AA)

 

existing acidity at this site would be classified as Category XH (extra high level) treatment in
accordance with SPP2/02 Guideline - Table 2.

The SPP2/02 Guidelines require that for Category XH treatment an EMP must be provided.
Furthermore Section 9.15 of SP2/02 Guidelines stipulates that “this plan should provide for
ongoing management and monitoring of the effects of disturbance of ASS through the
construction and operation of the project and describe the construction schedules and
environmental management procedures. The project should also be staged so that the
potential effects on any area disturbed at any one time is limited and easily managed.”.

Recommendations on strategies to be included in the EMP are discussed as follows.
6.7.1 Treatment of Excavated Soil

It is expected that earthworks on this site will comprise cutting and filling for roads and
trenching for the installation of various underground services. Management of soil excavated
below RL 5 m AHD is to be carried out as follows:

¢ Lime treatment is to be carried out on prepared pads and it would be prudent to make
such pads the permanent placement area. The earthworks strategy is to be formulated to
provide pads of appropriate size for practical spreading, mixing and drying, so that
adequate time is available to complete the treatment and validation before placing the
next layer.

e Stormwater should be diverted away from treatment/fill areas by clay bunds and/or
grassed swales.

e Treatment should be carried out by spreading the soil in maximum 300 mm loose
thickness layers and moisture conditioning before spreading lime at the appropriate
application rate. The soil may require reworking several times to achieve adequate
mixing of the neutralising agent and/or drying of the soil to optimum moisture content to
achieve compaction to an adequate engineering standard.

¢ It is proposed that the treatment level is based on the maximum values determined by this
investigation to be 5 kg.Lime/m? of soil excavated from 0.0 to 1 m and a rate of
18 kg.Lime/m! of soil excavated from below | m.

¢ Verification sampling and analysis is to be carried out on the treated soil to confirm that
appropriate amounts of the neutralising agent have been incorporated into the soil. Due to
the lack of pyritic material in the site soils, it is recommended that Total Potential Acidity
(TPA) testing would be an appropriate method for verification. Only verification samples
with laboratory pH values of less than pH6.5 would require analysis for remaining actual
acidity. Verification samples with laboratory pH values of greater than pH6.5 would not
require further testing.

Golder Associates

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Application part 2 [As Published].pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.