Flood Investigation & Stormwater Quantity Management Plan                                                    BROWN
                                                                                                                   Snuwt~
Proposed Residential Development at Doonella Stage C
                                               -




The developed scenario model results indicate that significant increases in peak flow to the site boundary occur for all
events modelled. Mitigation of the peak flow increases is required in order to ensure no adverse impact will occur on

downstream properties.


3.4        Management Strategy
Two detention storages are proposed to mitigate the increase in peak flows from the site. The two detention basins

are the   following:
The Dodonaea Close Basin

The construction of the road embankment across the environmental corridor at Dodonaea Close will effectively detain

flows from the upstream catchment. Flows through an optimally sized culvert underneath the crossing will control

outflows downstream.       Design of the crossing is to also ensure overtopping of the road embankment occurs during
high ARI events only, with the depth and velocity of overtopping flow limited to ensure the crossing is still trafficable.
Twigrush Court Bio-Retention Basin
The bio-retention basin at the lower end of Twigrush Court will also capture and detain flows from upstream sub-

catchments C1 and C2. Outflows from the bio-retention basin will be controlled by the bio-retention basin filter and

stormwater drainage field inlet located above the invert of the basin.

Refer to the concept basin designs on Drawing No. N09004.SK26 in Appendix D for details of the proposed detention

storages.

3.5        Mitigated Scenario
The two proposed detention storages have been entered into the WBNM                as   Outlet Structures.   Stage-Storage-
Discharge relationships have been used to model the change in water surface level and outflow from each detention
storage. The configuration for each detention storage is summarised below in Table 3.9. Refer to Appendix B for
detailed calculations used to generate the Stage-Storage-Discharge relationships.

                                   Table 3.9: Detention Storage Configuration Details

           Details                     Dodonaea Close Basin              Twigrush Bio.Basin
           Basin Invert RL (m.AHD)     9                                 7.5
           Basin Top RL (m.AHD)        12.25                             9.6

           Storage (m3)                2,520                             1,210
                                       1 x 450mm dia RCP, U/S IL         1 x 525mm dia RCP, U/S IL 6.9m.AHD,
                                       9.3m.AHD, D/S IL                  D/S IL 6.50m.AHD. RCP fed by 900mm x
           Outlet Structure            9.15m.AHD                         900mm field inlet at RL 9.00m.AHD.
                                                                         2 x 225mm dia RCP, U/S IL 7.8m.AHD.
                                                                         RCP’s within D/S wall of Bio-Basin.

                                       Road Crown, minimum level         5m Wide Weir at RL 9.3m.AHD
           Overflow Weir
                                       11.93m.AHD



The conceptual detention Stage-Storage-Discharge relationships were entered into the WBNM and run to determine
their effectiveness in mitigating the increase in peak flows resulting from the development. The results from the

mitigated scenario model are presented below in Table 3.10.




B09182.w-02A                                                                                                            Page 7

Used in these records

About this file

File size
35.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Pre-Request Response Application 132001.210310.1.pdf · 35.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.