Approved Decision Notice - MCU26 0040, OPW26 0066 & RAL26 0013 (As Published)
Easements
43. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
44. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
45. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
46. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be undertaken in accordance with the conditions
of this Decision Notice, be generally in accordance with Barlow Shelley’s Bulk Earthworks
Plan (C100, Rev. B) dated 8 May 2026 and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
47. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Page 8 of 27
Document Set ID: 25048906
Version: 6, Version Date: 13/08/2026