2017-01-16 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 16 JANUARY 2017
e. any landscaping, retaining walls, fences and fixtures near the access entry
point must comply with AS 2890.1 requirements for sight visibility for
pedestrians and cyclists at driveways
f. adjustment to any affected utility services in accordance with the
requirements of the relevant service provider.
Car Parking
17. A minimum of 33 car parking spaces and 4 motor cycle spaces must be provided
and marked on the site generally in accordance with the approved plans and in
compliance with Australian Standard AS2890: Parking Facilities for User Class
3A Table1.1. The works must be undertaken in accordance with an Operational
Works approval and must include in one (1) disabled parking space within the
total.
18. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
19. Prior to the submission of any Operational Works Application, the applicant must
provide a Traffic Management Plan for the refueling procedure that demonstrates
no adverse impact on traffic movements in Taylor Court or on the internal traffic
within the site. The plan should include any necessary time restrictions to be
implemented on refueling operation schedules to address the potential of
adverse impact on traffic.
20. All driveways, cars, motor cycles and bicycles parking areas must be line marked
in accordance with approved plan/s.
External Works Frontage Reinstatement Works
21. Frontage and external works be undertaken in accordance with an Operational
Works approval and must include in particular:
a. an extension to the existing concrete footpath to a new pram ramp facing
south direction at the intersection of Taylor Court and Holt Road in
compliance with current engineering standard drawings
b. all redundant driveways to the site must be removed and the kerb, footpath
and verge area are reinstated to match the balance of the site frontage,
including the provision of topsoil and turf where the existing verge is
grassed
c. replacement of any removed street trees
d. all necessary linemarking and other traffic measures in Taylor Court and
its intersection with Holts Road to improve traffic safety and address any
potential adverse traffic impacts caused by the increase in traffic generated
by the development.
This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009
being non-trunk infrastructure.
Pedestrian and Bicycle Facilities
22. Pedestrian and bicycle facilities must be provided for the development. The
works must be undertaken in accordance with an Operational Works approval
and must include in particular:
a. signage and lighting at strategic locations to direct people to building
entries.
Page 16 of 52
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.