MCU24/0084 Material Change Of Use - Function Facility – 658 Louis Bazzo Drive, Ringtail Creek · Attachment 2 - (MCU24 0084) - Planning Officer'S Report
PLANNING & ENVIRONMENT COMMITTEE MEETING REPORT 10 DECEMBER 2024
The Department has responded by providing their referral agency response. From a State referral
perspective, SARA have approved the development, subject to conditions. The conditions of their
approval require the existing access to be upgraded in accordance with the Department of
Transport and Main Roads (DTMR) standards. Road works comprising of a Basic Right Turn and
Basic Left Turn are to be carried out in accordance with DTMR requirements. Vegetation removal
and benching must be carried out to ensure sight visibility.
4.2. Internal Council Referrals
The application was forwarded to the following internal Council officers:
• Development Engineer
• Environment Officer
• Economic Development Officer
• Waste Management Officer
4.3. External Referrals
The application was forwarded to the following external parties:
• A peer review, requested by Council, of the Environmental Noise Level Impact Assessment
was carried out by MWA Environmental
4.4. Public Notification
The application was publicly notified for fifteen (15) business days in accordance with the Planning
Act 2016. 60 properly made submissions were received. The following table provides a summary
and assessment of the issues raised by submitters.
Matters Raised Comments
Submissions Against
Amenity Impacts The proposed development involves, weddings
and receptions, and has been assessed against
- Neighbourhood amenity will be
the requirements of the planning scheme in
impacted because of the proposed
relation to potential impacts on rural amenity and
use.
lifestyle, traffic and pedestrian safety.
- People bought in this area to enjoy
the peace and quiet. The application was subject to rigorous acoustic
- Increased visitors will result in an assessment, and included the requirement for
increased risk of theft and security further modelling by the applicant’s acoustic
issues. consultant to satisfy Council that the planning
scheme requirements in relation to noise and rural
amenity could be achieved.
The proposal can achieve the intent of the
Strategic framework as well as the Purpose,
Overall outcomes and Performance outcomes of
the applicable code, and the Overall outcomes of
the Rural zone code in relation to appropriate
management of adverse impacts on surrounding
sensitive land uses and maintenance of rural
character and amenity.
The application includes a comprehensive
Operational Management Plan which will
minimise any potential impacts on any adjoining
landowners and the community. The Operational
Management Plan, together with reasonable and
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.