Further Advice Response 17-07-25 22BRT0122_LT01_3 · OPW25/0042
The analysis indicates that the roundabout is expected to operate at suitable levels at the during the 2025
assessment year, with earthworks traffic included, with a worst-case DoS 44% (less than 85% - practical
capacity limit of roundabout) and overall LoS A. The addition of the Bulk Earthworks traffic has no notable
impact to key operational metrics, with minor change to average intersection delay and at most an increase
in queuing of 1 m (less than one vehicle length – approx. 6.0m).
Based on this SIDRA capacity assessment, the proposed Bulk Earthworks traffic generation is considered to
have negligible impact on the operations of the Noosa Drive / Coral Tree Avenue roundabout intersection.
Analysis of Grant Street / Noosa Drive / Sunshine Beach Road
Figure 3-3 shows the configuration of the Grant Street / Noosa Drive / Sunshine Beach Road roundabout
intersection adopted in the SIDRA analysis. All default SIDRA inputs were used for the analysis.
Figure 3-3: Grant Street / Noosa Drive / Sunshine Beach Road SIDRA Layout
Site: 3-7 Serenity Close, Noosa – Proposed Resort Complex
Reference: 22BRT0122
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Further Advice Response 17-07-25 22BRT0122_LT01_3.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.