2019-05-22 Special Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SPECIAL MEETING AGENDA 22 MAY 2019
5. Public Access to Sunshine Beach Skate Park
The Sunshine Beach Skate Park will remain operational during the NAC’s public closure.
Adequate public car parking will generally be available, however, there will be times where the
car park is closed for safety reasons. During such times the skate park may still be accessed by
utilising the linking pathway from Girraween Court.
Previous Council Consideration
Nil.
Finance
Council’s draft 2019/20 Capital Works Program includes funding for the proposed works within
the various asset management plan (AMP) renewal program items. The total cost of the works
falls within budgeted parameters.
Item Cost (excl. GST)
Costs to date (May 2019) nil
Tendered Contract Value $245,080.00
Superintendent Costs nil
Total Project Cost $245,080.00
Risks & Opportunities
Finance Risks Mitigation
Council requests for scope increases This is to be mitigated through the Project Control Group
(PCG) and Capital Works Executive (CWE) management
and limitation of client requested scope variations
Contractor claims for variations for Mitigation through PCG and CWE with allowances made
unforeseen issues. within the contingency.
Program Risks Mitigation
There is a potential that the project is Construction through the typically dry season aims to
delayed due to bad weather. mitigate this.
Materials supply. Continued communication and frequent meetings with the
contractor to ensure industry suppliers are providing
updates on project timing.
Resource risk Alto Pacific Pty Ltd has nominated a capable team
undertaking construction. The use of permanent NAC
staff to oversee works with assistance from others utilises
an existing Council resource.
Construction takes longer than allowed for. The contractor has demonstrated to be well resourced
and has allowed for ‘catch up’ days within their program.
Liquidated damages will apply if the nominated timeline is
not achieved by the contractor.
Major damage to 50m pool shell when Contractor must empty pool in line with controlled pool
emptying emptying requirements. Contractor will be asked to
develop a risk plan specifically around this item in order to
identify required actions should issues arise.
Page 11 of 14