SPECIAL MEETING AGENDA 22 MAY 2019
4. Program
As part of the tender clarification process, Ri-Con Contractors Pty Ltd clarified that completion of
the project could be accomplished in line with Council’s anticipated timeline, weather permitting.
The NAC will be closed to the public throughout the works which will also coincide with other
major works at the NAC within the 50m pool and plant room. Regular NAC attendees have
already been notified of the anticipated facility closure and will receive a more detailed update
following the award of the tender.
5. Public Access to Sunshine Beach Skate Park
The Sunshine Beach Skate Park will remain operational during the construction project.
Adequate public car parking will generally be available, however, there will be times where the
car park is closed for safety reasons. During such times the skate park may still be accessed by
utilising the linking pathway from Girraween Court.
Previous Council Consideration
Nil.
Finance
Council’s draft 2019/20 Capital Works Program includes $350,000 funding for this capital project,
comprising $232,500 (excl. GST) for roof replacement and $117,500 for deck replacement (excl.
GST) as part of the asset management plan renewal program. All tender submissions came in
over budget to varying levels. It is proposed that the additional costs required to complete the
project be incorporated into the budget as part of the 2019/20 BR1 budget review in August
2019.
Item Cost (excl. GST)
Costs to date (May 2019) $12,228.50
Tendered Contract Value $364,644.00
Superintendent Costs $4586.50
Total Project Cost $381,459.00
Risks & Opportunities
Finance Risks Mitigation
Council requests for scope increases This is to be mitigated through the Project Control Group
(PCG) and Capital Works Executive (CWE) management
and limitation of client requested scope variations
Contractor claims for variations for Mitigation through PCG and CWE with allowances made
unforeseen issues. within the contingency.
Program Risks Mitigation
There is a potential that the project is Construction through the typically dry season aims to
delayed due to bad weather. mitigate this.
Materials supply. Continued communication and frequent meetings with the
contractor to ensure industry suppliers are providing
updates on project timing.
Page 5 of 14