6.2 Operational Phase
The proposed development involves the development of land greater than 2,500m2.
Consequently, State Planning Policy 2014 (SPP 2014) is triggered.
Water quality objectives (WQO’s) for South East Queensland as set out in the Urban Stormwater
Quality Planning Guidelines 2010 should be achieved by identifying and adopting best practise
techniques in accordance with the abovementioned guidelines. Refer to Table 6.2 for target
WQO’s.
Table 6.2 – Minimum Mean Annual Load Reductions
Minimum Mean Annual
Contaminant
Load Reductions
Total Suspended Solids (TSS) ≥ 80%
Total Phosphorus (TP) ≥ 60%
Total Nitrogen (TN) ≥ 45%
Gross Pollutants (GP) ≥ 90%
6.2.1 Sources of Contaminants
Potential sources of contaminants and stormwater quality improvement devices identified for
the operational phase of the development are outlined in Table 6.3.
Table 6.3 - Sources of Contaminants
Pollutant
Target Pollutant Type Acceptable Treatment Examples
Size
Primary Screening of gross Litter baskets, swales, buffer strips,
>5000um
Pollutants pollutants GPT’s, rainwater tanks with re-use
Sedimentation of
Secondary 125um - Swales, sedimentation basins, ponds,
coarse to medium
Pollutants 5000um rainwater tanks with re-use
sediment
Enhanced Bio-retention basins, constructed
10um –
sedimentation of fine wetland macrophyte zones, other bio
125um
particulates technologies
Tertiary Adhesion and filtration
0.45um – Constructed wetland macrophyte zones,
Pollutants of very fine / colloidal
10um other bio technologies
sediment
Biological uptake of Constructed wetland macrophyte zones,
<0.45um
dissolved particles other bio technologies
Site Based Stormwater Management Plan
Proposed Medical Development at Cnr Val Crescent & Goodchap Street, Noosaville
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Stormwater Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.