$3.4 Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site,
the new site or between the sites is repaired or reinstated to at least pre-existing conditions.

As per the DA, all areas will be either new or reinstated as per the approved plans.
$4.17 Waste materials are removed from the site;

All demolition materials will be removed from site as per the contractors approved trucks in
accordance with all guidelines.

and

$5.1 Erosion and sediment control measures are installed and maintained until soils are stabilized by
vegetation or sealed.

As detailed in the BA plans, Hydraulic drawings show the Erosion and site sediment plan.
and

S6.1 If a development permit has not been issued for the future use of the site—

a) Hard surfaced areas including concrete slabs are removed or covered with a minimum of 300mm of
soil; and

b) Disturbed areas are revegetated using. species identified in PSP3 — Landscaping Plants and
Guidelines, :

Submitted

“Waste that cannot be collected by Council's normal collection service is collected by an approved
Regulated Waste Transporter.

4.2 An area is to be allocated on the development site for the segregation of construction and
demolition materials. Details of the site area to be used for on-site separation, treatment and storage
(including weather protection) are to be provided on the plan drawings accompanying the application.

During the demolition phase the contractor requires no on site holding or separation areas.

 

Used in these records

About this file

File size
4.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

09_1508 - Operational Works - Landscaping. Stormwater, S&E Control, Carparking & Acess, Frontage Works [As Published].pdf · 4.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.