SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 APRIL 2022
Therefore, staff will:
- Submit a request for an increase in grant funding for the Cooroy Belli Creek Road Bridge on a
50-50 basis for the budget shortfall.
- Withdraw the Lawnville Road Bridge project grant funding from the Bridge Renewal Program,
round 5.
- Reapply for grant funding for the Lawnville Road Bridge project under the Bridge Renewal
Program, round 6:
i. with a revised cost estimate.
ii. reschedule the Lawnville Road Bridge Replacement project in the capital works program if
successful. The revised funding strategy is summarised and detailed in the tables below:
Cooroy Belli Creek Road Bridge replacement, project cost
Item Cost (excl. GST)
Costs Year to Date (March 2022) $163,000
Tendered Contract Value $1,011,420
Consultants, staff and superintendent costs, levies, and project allowance $219,110
Total project cost $1,393,530
Cooroy Belli Creek Road Bridge replacement, funding strategy
Funding source Cost (excl. GST)
Currently approved grant contribution $450,000
Currently approved Council contribution $450,000
Subtotal – currently approved $900,000
Additional grant increase (request to Federal Bridges Renewal Team) or reallocate $246,765
part of the grant contribution from Lawnville Road Bridge
Additional Council contribution increase (either cash reserves or utilising part of the $246,765
existing Council contribution from Lawnville Road Bridge project)
Subtotal – additional $493,530
Total project funding amount, matching required project budget $1,393,530
If Council is unsuccessful in obtaining the additional grant increase, a larger part of the existing
Council contribution for Lawnville Road Bridge project funding will be utilised to cover the shortfall.
Risks & Opportunities
Finance Risks Mitigation
Council request for scope This is to be mitigated through the Capital Works Project Control Group and
increases. Capital Works Executive meetings and limitation of client requested scope
variations.
Scope changes once Council acceptance of scope as awarded with intention of not increasing
construction commences scope.
and project becomes
publicly visible.
Geotechnical conditions A detailed Geotechnical investigation report has been completed and the
give rise for contractor report provided as part of the tender documentation. Any required variations
claiming variation costs. in depth will be worked out by variation rates that have already been locked in
with the contractor as part of the contract specifications. A budget
contingency allows for this risk.
Page 7 of 40
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.