2022-04-12 Services & Organisation Committee Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 APRIL 2022
Finance Risks Mitigation
Subgrade material found The contract specifications specify clearly how and until what extent the
to be unsuitable for reuse existing subgrade material needs to be processed to reuse these materials.
purposes within the In case a certain amount is not found suitable, locked in rates are in place. A
projects. budget contingency allows for this risk.
Clashes with public utility The contractor is aware of nearby underground Telstra / NBN cables. It’s the
provider Telstra / NBN contractor’s responsibility to initiate a Dial Before You Dig procedure and
give rise for contractor prevent any impact to the Telstra / NBN network. The Contractor is
claiming variation costs. responsible for any cost of repairs if these services get damaged during
construction.
Contingency amount This risk is mitigated through Council's highly experienced project team and
being insufficient. the appointment of an experienced contractor and contract supervision by an
experienced Superintendent. Any delay risks forthcoming of the current
pandemic is not included in the contingency amount. If the contingency
amount is insufficient to cover the cost, this is to be mitigated though the
budget approval process.
Program Risks Mitigation
There is the potential that The contractor allowed for wet weather delay days in its program based on
the project is delayed due past weather data from the 2021 calendar year. If additional wet weather
to wet weather. delay days are required, the experienced superintendent will follow the
process which is embedded in the contract specifications. Moreover, the
contractor’s timeline shows an earlier completion date then prescribed in the
tender specifications, which gives additional room to mitigate an unforeseen
construction delay.
Resource risk. The contractor has nominated a capable and experienced project team to
undertake construction.
Construction takes longer The contractor is well resourced and has the available resources to deliver
than allowed for. this project successfully in conjunction with current works on hand. The use
of pre-cast concrete deck units reduces the risk of construction delays.
Lead time of materials Many associated risks are mitigated by ordering the materials as soon as
pushing the program out. possible after the tender award. It has been identified that the pre-cast
concrete deck units may have lead time issues, mainly due to high demand.
The contractor is aware and will manage this risk and work closely together
with Council's project team to minimise residual timing risk.
The contractor confirmed that if this risk occurs, there will be no cost variation
to Council, if we award the tender on 22 April 2022.
Staff capacity of Council’s Procurement team is sufficient to meet this
deadline.
Safety Risks Mitigation
Site safety The contractor has extensive experience with similar works and would be
appointed as the Principal Contractor, being responsible for all Workplace
Health and Safety of the site.
Prior to construction commencing, workplace health and safety and
construction management plans will be required to be submitted to Council
for review.
Regular audits on contractor compliance with these approved plans will be
undertaken by Council and WH&S teams throughout the construction.
High-risk work using The contractor is accredited to AS 45001 (Occupational Health & Safety
machinery and hoisting Management) and the contractor has demonstrated their capability through
involved. the tender process.
The contractor is experienced having successfully completed several similar
types of bridge replacement projects within the past years, moreover the
contractor was principal contractor for the Cooroy, Mary River Road Bridge
replacement project, which was completed in early 2019.
Page 8 of 40
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.