Nandroya Planning Report

Attached to the e-mail MCU16/0066_Further info re: Representations regarding stormwater 6 Taylor Court Cooroy.msg.

of 71

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

leddy sergiacomi &
associates pty. Itd.

LSA Ref: 45-021

 

2.3.7

2.4

Project Services have since commissioned Douglas Partners to submit a Stage 2 investigation to
the EPA, to undertake necessary remediation work and have the site removed from the register.
It is also understood that a further commission will be issued to have the buried timber removed
from the site, demolish the existing unused buildings and have the site prepared for development.
This will allow the unrestricted development of the subject land once development approval has

been granted.

Summary of Soil Investigation

Based on the results of the field and laboratory investigations, the findings have been
summarised below:

> Soils have been classified having a reasonable bearing capacity (>200kPa), and moderately
reactive (Class M);

Stable fill batter slopes should be not steeper than 1V:2H;

The soil is relatively non-dispersive;

Field permeability test displayed low values, indicating constraints with soil permeability,

Vv VV

Soils on the site consist mainly of high plasticity clays which are considered suitable for the
proposed subdivisional works; and .

> For pavement design purposes a subgrade strength of CBR4 is suggested.

HYDROLOGY & DRAINAGE

The site drains from a ridge line located generally through the existing mill buildings in the
northern area of the site to a series of dams strategically positioned around the site. A series of
small piped systems drain the existing roof areas of the mill buildings to open drains which are
directed in turn to the existing dams. One dam is located in the north western comer of the site, a
second dam in the central southern portion of the site and the third in the south eastern corner of
the site. The third dam (south-east comer) is the larger of the dams and accepts run-off from over
half of the site mainly due to a diversion drain constructed generally along the southern area of
the property. This drain limits the catchment to the central dam (south) to a small flat area in the
southern portion of proposed Lot 5. Both the dams in the southern area of the site overflow to a
creek system located in the adjacent property to the south, the creek then discharging under Holts

Road and the Bruce Highway through a 3.3 metre diameter corrugated steel culvert.

 

14 November 2005 Department of State Development, Trade and Innovation Page: 7

Planning Report
Log in to download the original file

Nandroya Planning Report.pdf · 8.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.