A program of works is to be submitted with any application for any Development Permit
for Operational W orks detailing the construction schedule and proposed environmental
protection measures.

Where the program is changed for any reason whatsoever, a copy of the revised
program shall be submitted to Council's Works Inspector within seven (7) days.

For the following classes of work associated with development, a Development Permit
for Operational W orks must be obtained prior to commencement of works relating to
that class of work. The application may combine any or all of these classes of work:-
133.1 Site Civil Works

133.2 Roadworks

133.3 Stormwater Drainage

133.4 Frontage works

133.5 Sewer reticulation including new mains, relocations, diversions, pump stations
and rising mains

133.6 Water reticulation

133.7 Site Filling

133.8 Excavation of materials to fill another site

133.9 Landscaping.

Operational works shall be carried out in a manner that prevents :-
131.1.Pollution of a waterway

131.2.Dust/sand nuisance to residents in the vicinity

131.3, Transfer of dirt and debris onto a public road

131.4,Excessive notice (less that 1.5 Dba above ambient measured at the lot
boundaries)

131.5.Excessive traffic delays (less than 5 minute delays)

131.6. Diminution of neighbourhood amenity (long term parking of employees vehicles,
parking of construction equipment etc.)

A traffic management plan shall be submitted in conjunction with a Development Permit
for Operational Works involving road or drainage works. The plan shall address all
phases of construction to be undertaken on site.

Where operational works are likely to effect nearby residents and the Noosa Primary
School, at least 3 days notice of commencement of work, the name of the site
supervisor and a 24 hour contact telephone number shalt be distributed to affected
results.

Earthworks shall be generally contained within existing and proposed road reserves.

Where earthworks are required for the provision of services, existing contours shall be
restored.

-24-

Used in these records

About this file

File size
4.4 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

23616 DA - Change a Development Approval [As Published].pdf · 4.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.