Appendix F - engineering report
Attached to the e-mail MCU15/0111 & REC15/0031 Development Application F - Engineering report Email 7 of 8.
CALIBRE CONSULTING
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
O1 Water Supply Infrastructure S1.1 Water supply infrastructure is A water supply analysis has been
designed in accordance with Section undertaken. The results of the study
(a) Meets the needs of the users;
3 of PSP 6 – Engineering Design indicate that sufficient capacity is
(b) Is designed to be compatible Standards – Water and Sewerage available for the proposed
with existing infrastructure; and As Constructed data submitted in development.
and accordance with Section 7 of PSP 6 –
Engineering Design Standards –
(c) Is deigned using materials Water and Sewerage.
that are suitable for the use,
durable, easy to maintain and
cost effective, taking into
account the whole of life cycle
cost and Council’s
maintenance inventory.
O2 Water supply infrastructure is S2.1 Water supply infrastructure is All water supply infrastructure will be
constructed: constructed in accordance with constructed and tested in accordance
Section 6 of PSP 6 – Engineering with Council requirements.
(a) in accordance with
Design Standards – Water and
appropriate engineering
Sewerage;
standards; and
AND
(b) to minimise adverse
environmental impacts.
S2.2 Erosion and Sediment control Erosion and sediment control
measures are designed and measures will be prepared as part of
implemented in accordance with the the operational works (civil) design
Institution of Engineers Australia (Qld drawings.
Division) Soil Erosion and Sediment
Control – Guidelines for Queensland
Construction Sites.
O3 Water supply infrastructure is No solution provided. Water supply infrastructure will be
proven to be suitable for its use constructed and tested to Council’s
prior to Council accepting the satisfaction prior to hand over.
dedicated asset.
O4 Water supply infrastructure is No solution provided. Water supply infrastructure will be
provided with all supporting supported by all required technical
technical documentation. documentation.
O5 Where buildings or other S5.1 The footing of any building or All existing infrastructure will be
structures are in proximity to structure is located clear of the zone protected from the proposed works.
Council’s water supply of influence but no closer than 1.5m
infrastructure, provision is made to (measured horizontally) from
protect the infrastructure from infrastructure including sewers, water
physical damage and to allow mains and stormwater structures.
ongoing maintenance by Council.
AND
S5.2 A registered easement in favour
of Council is created over all
underground infrastructure located in
private property;
AND
B14158.W | COOROY RETIREMENT COMMUNITY | PALM LAKE RESORTS CIVIL ENGINEERING REPORT | 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.