Water & Sewer Connections
18. An underground connection to reticulated water and sewerage must be provided to the
premises in accordance with the standards and requirements of Northern SEQ Distributor–
Retailer Authority (Unitywater).
19. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the premises.
Landscaping
20. The development site must be landscaped. The works must be undertaken in accordance
with an Operational Works approval and the Noosa Plan for that specific area and must
include in particular:
a. the works shown on the approved landscape plans.
b. vegetated screening of any electrical transformers, bin storage areas and the like from
the road frontage
c. provision of 1 street tree within the road reserve for every 8 metres of road frontage,
where practicable
21. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
External Works
22. Bottlebrush Ave must be upgraded for the length of its frontage to the subject site. The works
must be undertaken in accordance with the conditions of this Decision Notice and be
generally in accordance with Barlow Shelley’s Roadworks & Drainage Layout Plan (C200
Rev A) dated 15/05/2026 and must include in particular:
a. construction of a pedestrian footpath in accordance with the conditions of this Decision
Notice; and
b. removal of the existing property access and reinstatement of the kerb, footpath and
verge area to match the balance of the site frontage, including the provision of topsoil
and turf where the existing verge is grassed.
Site Access and Driveways
23. A sealed access driveway must be provided from Bottlebrush Ave to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
the conditions of this Decision Notice and be generally in accordance with Barlow Shelley’s
Roadworks & Drainage Layout Plan and Driveway Details (C200 Rev A & & C210 Rev B)
dated 15/05/2026 and 20/05/2026 and must include in particular:
a. a driveway crossover generally in accordance with Council standard drawings RS-049
& RS-050.
Car Parking
24. A minimum of 7 car parking spaces must be provided and marked on the site. The works
must be undertaken in accordance with the conditions of this Decision Notice and be
generally in accordance with Barlow Shelley’s Roadworks & Drainage Layout Plan (C200
Rev A) dated 15/05/2026 and must include in particular:
a. visitor parking spaces within the total, which are clearly marked for that purpose and
accessible at all times for visitor use; and
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Page 20 of 33
Document Set ID: 24436845
Version: 6, Version Date: 09/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU26 0001 - AS PUBLISHEDRelated documentApplication case desk ↗
About this file
- File size
- 8.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.