Car parking is located to the rear of or under a building and screened from the street, or
otherwise without a presentation to the primary frontage and with good connectivity for
pedestrians to other destinations within the precinct.
Under the Noosaville Local Plan Code, overall outcome (e), states:
Development design and siting responds to the relatively flat topography of Noosaville by
creating visual interest and differentiation in built form through design and the application of:
a) a range of textures, colours, styles and finishes;
b) a range of architectural elements within the context of a sub-tropical architectural theme;
c) varied roof heights, that cumulatively make a positive contribution to an interesting
skyline;
d) varied setbacks which create opportunities for both landscaping and design variety; and
e) retention of mature trees and the provision of new landscaping which create attractive
spaces between buildings.
While the Landscape Concept Design report provides a response to the Landscape Code at
part 5.1, there are no comments provided explaining how the development as a whole meets
the overall landscaping objectives for the NBC, including being consistent with a Noosa Style.
Landscaping is to be integrated with the built form and provide for significant areas of deep
planting.
The report claims the proposal complies with all the applicable provisions; however, it is
unclear if compliance is with the acceptable outcomes (AO) and/or the performance outcomes
(PO). Further, how the landscaping will be integrated with built form and the expected with the
village green and open space is not adequately explained.
Further Information:
36. Provide a summary of landscape areas and number of canopy trees to demonstrate
compliance with AO11.1 and AO11.2 or otherwise how the development meets the
performance outcome 11.
37. Provide landscape elevations of the Main Street (including under croft frontage), Civic
Spine and eastern car park to demonstrate compliance with performance outcomes
PO2, PO3, PO5, PO6, and PO11. Landscaping should be depicted at 5 years growth.
Issue – Flooding, stormwater quality, water efficiency and reuse
Issue – Flooding
The natural drainage channel within Covenant J on Lot 1 provides conveyance for most of the
“Noosa Civic” site. Peak flood levels within this channel need to be established in order to
demonstrate that the development will achieve adequate freeboard and flood impacts will not
result from the works.
Information Required
38. Provide calculations/modelling for flow within the natural drainage channel within
Covenant J on Lot 1 in order to establish the peak flood levels in the DFE (1%AEP
including allowance for climate change at 2100). Provide sections which show the DFE
level relative to the minimum opening elevations in the basement car park and
demonstrate that a minimum freeboard of 300mm is provided.
Issue – Stormwater Quantity
The analysis of stormwater quantity impacts is required to include allowance for climate
change, and it is not clear whether this has occurred. Detention to mitigate the 63%AEP in
Page 15 of 21
Document Set ID: 22464338
Version: 2, Version Date: 17/07/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Information Request MCU23 0078 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 187 KB (small file)
- File type
No other editions are linked here.