Final Options Analysis Report (Corridor 2)
Despite this, the low speed (30km/h), the design of the cycle street and the provision of pedestrian footpaths on the
eastern side of Tristania Drive will ensure this is a safe facility for all ages and abilities.
Segment 5: Peregian Beach North
Y
While Option A (cycle street → village scale cycle track) for Segment 5 received the highest score in the MCA, this is not
considered the preferred option. In light of the broader context and feedback from the PWG, Option C (shared path) is
the preferred off-road option for Segment 5 as it provides excellent consistency in the type of the facility treatment
LIC
proposed, as it benefits pedestrians by addressing existing gaps in the footpath network, and as it supports current NSC
planning for a portion of the segment.
Segment 6: Peregian Beach South
Option A (cycle street) is the preferred off-road design treatment for Segment 6 as it received the highest score in the
MCA, as it is cost effective, as it is appropriate to the local context and as it achieves LTS 1. Although the proposed
PO
treatment will be provided on the existing road surface, it will form part of the off-road coastal corridor. This option does
not provide dedicated space for cyclists along Plover Street, Piper Street, Shearwater Street and Lorikeet Drive which may
reduce the perception of safety for some users. Despite this, the low speed (30km/h), the design of the cycle street and
the provision of pedestrian footpaths on the eastern side of these streets will ensure this is a safe facility for all ages and
abilities. As a possible ultimate/long term option, there is potential to implement an off-road bushland path located
between residential properties and the beach (refer to Figure 25). This option will be subject to cost, feasibility,
environmental assessments and community feedback.
Table 35: Preferred design options – links (off-road)
SEGMENT / OPTION DESIGN DESCRIPTION
CIL JUSTIFICATION & IMPLEMENTATION CONSIDERATIONS
Segment 1: Noosa Drive
Design Option C Separated path through Lions Final alignment and design of the cycle facility in the vicinity
Park, a cycle street on Noosa of Lions Park subject to other NSC planning. Design to
Drive Service Road West and a consider connectivity to Hastings Street and use of Lions
N
village scale cycle track on Park, including for Noosa Triathlon.
Noosa Drive.
Appropriate cycle crossing required at Noosa Drive/Sunshine
Beach Road roundabout.
OU
Segment 2: Noosa Junction
Design Option B Village scale cycle track along Possible to provide a two-way village scale cycle track on
Sunshine Beach Road. northern side of road, reducing south bound traffic lane to
one lane but not impacting north bound traffic lanes.
Appropriate cycle crossing required at Noosa Drive/Sunshine
Beach Road roundabout.
TC
Segment 3: Sunshine Beach
Design Option C Shared path along Pacific Shared path to be implemented on eastern side of Pacific
Avenue and Hill Street. Avenue with potential future village scale cycle track.
Placement of shared path is important as it will allow for re-
use as wide footpath once adjacent village scale cycle track is
implemented.
NO
Segment 4: Marcus Beach
Design Option A Cycle street along Tristania Loss of parking on one side of Tristania Drive.
Drive.
Cycle street to be implemented with consideration of a
footpath on the eastern side of Tristania Drive.
Segment 5: Peregian Beach North
Design Option C Shared path along Peregian Integrate with existing NSC path upgrade plans for Osprey
Esplanade, Osprey Avenue Drive.
and Kingfisher Drive.
0996 – 24 February 2021 – V2 The analysis, design and cost estimating referenced in the report was63undertaken
solely to guide planning and should not be interpreted as a final or endorsed
position of Noosa Council.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Noosa High Priority Cycle Route Corridor Study(PDF, 8MB).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.