Noosa High Priority Cycle Route Corridor Study(PDF, 8MB)
Noosa High Priority Cycle Route Corridor Study and Concept Design
Final Options Analysis Report (Corridor 2)
SUB-TOTAL TOTAL
ID LOCATION DESCRIPTION OF WORKS PRIORITY 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30
(10-YEAR) (10-YEAR +)
2.8 Ross Cres Construct cycle street and footpath H $164,732 $21,634 $186,366 $186,366
2.9 Sobraon St/ Tingira Cres Construct cycle street and footpath H $583,562 $583,562 $583,562
2.10 David Low Way (Sunrise Beach) Upgrade to 3.0m shared path M $0 $748,566
2.11 David Low Way (Castaways Beach) Upgrade to 3.0m shared path M $0 $1,558,451
The analysis, design and cost estimating referenced in the report was undertaken
2.12 David Low Way (Marcus Beach) Upgrade to 3.0m shared path M solely to guide planning and should not be interpreted as a final or endorsed $0 $926,351
position of Noosa Council.
C Y
2.13 Tristania Dve Construct cycle street and footpath H $194,804 $123,289 $318,093 $318,093
O L I
2.14 David Low Way (Glen Eden) Construct 3.0m shared path H $550,796 $550,796 $550,796
L P
Peregian Esp/ Osprey Ave/
I
2.15 Construct 3.0m shared path H $125,915 $800,000 $925,915 $1,056,039
Kingfisher Dve
N C
2.16 Peregian Beach Construct 3.0m shared path H $0 $213,486
O U
2.17 Plover St/ Piper St Construct cycle street H $190,526 $190,526 $190,526
T C
2.18 Shearwater St/ Lorikeet Dve Construct cycle street H $84,254 $523,303 $607,557 $607,557
N O
CORRIDOR 2 SUB-TOTAL $0 $21,633 $800,000 $800,000 $523,303 $291,123 $380,267 $800,000 $800,000 $800,000 $5,216,326 $14,660,548
HPR PROJECT TOTAL (CORRIDOR 1 & 2) $558,000 $800,000 $800,000 $800,000 $800,000 $800,000 $765,780 $800,000 $800,000 $800,000 $7,723,780 $18,737,335
*Cost of new/upgraded cycle facility as per this report not included in estimate.
^Cost as per current Noosa Shire Council 10-year Capital Program. These costs are included in the draft implementation plan but not in the estimate to implement the HPR.
0996 – 24 February 2021 – V2 78
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Noosa High Priority Cycle Route Corridor Study(PDF, 8MB).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.