               56.    A log book for the Erosion and Sediment Control measures and inspections must be
                      maintained by the site manager and made readily available to Council when requested. The
                      supervising engineer must verify and endorsed the E&SC measures upon their installation,
                      and periodically check these measures and the log book during construction and the
                      stabilisation stages. Any defects in erosion and sediment control devices, such as sediment
                      fences, are to be inspected and documented. Upon Inspection, the contractor is to determine
                      whether the device should be replaced or repaired. Documentation is to include how the
                      damage was caused and what measures can be implemented to reduce the possibility of
                      repeat occurrences. Any damage to either permanent or temporary water quality control
                      structures or devices is to be immediately rectified at the contractor’s expense.
                      The effectiveness of the erosion and sediment control devices must be monitored. All ESC
                      measures are to be inspected:
                      a.      at least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      b.      within 24 hours of expected rain; or
                      c.      within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
                      Landscaping
                      Retention of Existing Trees and Vegetation
               57.    All trees and vegetation identified for retention must be protected in accordance with AS
                      4970, Protection of trees on development sites.

                      Fauna Management
               58.    A qualified person* must be engaged to manage fauna prior and during clearing to:
                      d.      Ensure works are carried out in accordance with the referenced Fauna Management
                              Plan J001343 dated Sept 2024; and the Nature Conservation Act 1992.
                      e.      Undertake pre-clearing inspections including fauna relocation and removal or blocking
                              of all vacant hollows.
                      f.      Ensure clearing works avoids nesting times of animals and birds.
                      g.      Co-ordinate staging and sequence of clearing with fauna protection.
                      h.      Protect and recover fauna during clearing operations (not previously removed).
                      i.      Manage the translocation of animals and recovery procedures in accordance with
                              relevant legislation.
                      *(Refer to Advisory Note)
                      Plant Pest Management
               59.    A qualified person* must manage plant pest (weeds) to:
                      a.      Ensure plants listed as Class 1 and 2 declared pests within Council’s Pest
                              Management Plan are controlled and prevented from spreading.
                      b.      Oversee management techniques that minimise regrowth, prevent damage to non-
                              target species, retain conservation values and maintains site stability.
                      *(Refer to Advisory Note)
                      Landscaping Works
               60.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice and must include in
                      particular:
                      a.      Substitution of Ficus Obliqua with Syzygium leuhmannii
                                                                                                        Page 17 of 23

Document Set ID: 23977399
Version: 6, Version Date: 22/08/2025

Used in these records

About this file

File size
1.1 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW25 0057.pdf · 1.1 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.