61. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
62. Landscape works must:
a. Ensure amenity or sales signage and ancillary infrastructure is not installed within the
road reserve.
b. Ensure permanent irrigation is not installed within the road reserve.
c. Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
applied to all planting areas to ensure a minimum 100mm depth once settled.
*(Refer to Advisory Notes)
63. Public amenity trees* must:
a. Meet Specifying Trees – a guide to assessment of tree quality (NATSPEC).
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
*(Refer to Advisory Note)
64. Turfed areas must be must be free of pest, diseases and weeds and level with adjoining
surfaces.
FOLLOWING CONSTRUCTION / COUNCIL SIGNING THE PLAN OF SURVEY
Certification
65. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
As Constructed Plans and ADAC XML Files (Council)
66. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
information shall include:
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
a. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
information, levels and applicable survey datum.
Page 18 of 23
Document Set ID: 23977399
Version: 6, Version Date: 22/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW25 0057.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.