4.9 Is the work for other work for taking or interfering with water?

 

 

No | End of part 4 of this checklist

 

[-] Yes | + Adevelopment permit is required and this application will be assessed by the chief executive of

resources state code in the SDAP
e You must complete DAS form 21—Other work in a watercourse
e — End of part 4 of this checklist

 

DSDIP as assessment manager or concurrence against the Sustainable management of water

 

 

Part 5—For particular dams

 

 

5.1 Is the proposed operational work for the following?

 

 

The construction of a dam more than 10 metres in height and having a storage capacity of
more than 1500 megalitres

LE] Yes No

 

The construction of a dam more than 10 metres in height and having a storage capacity of
more than 750 megalitres and a catchment area that is more than three times its maximum
surface area at full supply level

| Yes No

 

Work carried out in relation to an existing non-referable dam that will result in the dam being
more than 10 metres in height and having a storage capacity of more than 1500 megalitres

Cl Yes No

 

Work to an existing non-referable dam that will result in the dam being more than 10 metres in
height and having a storage capacity of more than 750 megalitres and a catchment area that
is more than three times its maximum surface area at full supply level

CT Yes &X No

 

Works that involve the increase of capacity of a non-referable dam by more than 10 per cent if
the dam is:

more than 10 metres in height and having a storage capacity of more than 1500
megalitres, or

*® more than 10 metres in height and having a storage capacity of more than 750
megalitres and a catchment area that is more than three times its maximum surface area
at full supply level

im Yes Xx] No

 

Works carried out in relation to a referable dam if, because of the works, the storage capacity
of the dam will increase by more than 10% after the works are carried out.

| Yes Xl No

 

 

Constructing a dam for which the chief executive under the Water Supply (Safety and
Reliability) Act 2008 has given a notice to have the dam failure impact assessed.

 

Ol Yes Xx] No

 

« If no to all of the above, the proposed operational work is not required to be failure impact assessed and is

therefore not assessable development. This is the end of part 5 of this checklist

e — If yes to any of the above, this application requires assessment by the chief executive of DSDIP as assessment

manager or concurrence agency against the Particular dams state code in the SDAP.
- You must complete /DAS form 16—Particular dams
- End of part 5 of this checklist

 

Part 6—Tidal work

 

 

6.1 Is the proposed tidal work any of the following:

 

 

Excluded work

Cc] Yes No

 

Work that is self-assessable development under schedule 3, part 2, table 4, item 8 of the
Sustainable Planning Regulation 2009

C] Yes No

 

 

Work carried out in a priority development area

 

Cl Yes No

 

 

 

Checklist 4—Operational work
Version 4.1—-1 October 2074

Used in these records

About this file

File size
2.0 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

OPW14_0362 Operational Works for reconstruction of stormwater pit.pdf · 2.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.