PROJECT URBAN – 20153                                                                              13 Jul 2020


 Performance Criteria             Acceptable Solution                            Comments
 Design, construction and safety – all prescribed tidal work
 12.4 Prescribed tidal works The design and construction of the                  Compliant.
 are        designed         and prescribed tidal works is consistent with
 constructed using materials the following standards:-                           The proposed structure will be
 suitable        for      marine a) subject to paragraph (b), each               constructed utilizing materials
 environments,            having     Australian Standard relevant to the         that have a long life and are
 regard to their ability to          materials that should be used, or the       resilient to marine organisms,
 resist the following:-              measures that should be taken to treat      corrosion and saltwater. The
 a) attack        by      marine     materials used, for structures, to the      engineered plans show the
      organisms;                     extend the requirements stated in the       materials used.
 b) corrosion;                       Standard apply to structures located in
 c) deterioration              or    a marine environment;
      breakage resulting from b) if a relevant planning scheme standard
      exposure                 to    is more stringent than the standard
      environmental                  mentioned in paragraph (a) – the
      conditions including, for      relevant planning scheme standard, to
      example, the following:-       the extent it is more stringent than the
          (i)        abrasion;       standard mentioned in paragraph (a).
          (ii)       immersion
                     in seawater;
          (iii)      wave
                     action.
 12.5 Prescribed tidal works The design and construction of the                  Not applicable.
 are        designed         and prescribed tidal works is consistent with
 constructed in a way to the following standards:-                               There are no stormwater
 ensure       they     do    not a) subject to paragraph (c), vessels            outlets near the proposal.
 adversely        affect     the     moored at prescribed tidal work do not
 operation or maintenance            impede the discharge of stormwater;
 of any existing stormwater b) subject to paragraph (c), prescribed
 outlet.                             tidal work does not restrict access to
                                     any stormwater outlet;
                                  c) if a relevant planning scheme standard
                                     is more stringent than the standard
                                     mentioned in paragraph (a) – the
                                     relevant planning scheme standard, to
                                     the extent it is more stringent than the
                                     standard mentioned in paragraph (a)
                                     or (b).
 12.6 Prescribed tidal works The design and construction of the                  Compliant.
 are        designed         and prescribed tidal works is consistent with
 constructed in a way to the following standards:-                               The proposed structure will
 ensure       they     do    not a) subject to paragraph (b), each               involve only minimal and short
 adversely affect the water          Australian Standard relevant to the         term disturbance to the canal
 quality of any tidal water,         design or construction of structures        bed during the works. There
 including, in particular, as a      under, within or over tidal water, to the   will be temporary sediment
 result of:-                         extent the requirements stated in the       control measures put in place
 a) release, into the tidal          Standard are directed at maintaining        to      keep       disturbance
      water, of materials used       the water quality of tidal water;           minimalized for the duration of
Development Assessment Report                                                                       Page 22 of 42
Operational Works
37 Mossman Court, Noosa Heads 4567
Log in to download the original file

05. Hales - Planning Report.pdf · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.