05. Hales - Planning Report
Attached to the e-mail Operational Works Application OPW20/0117 - 37 Mossman Crt Noosa Heads.
PROJECT URBAN – 20153 13 Jul 2020
Performance Criteria Acceptable Solution Comments
Design, construction and safety – revetments and seawalls
erosion at the base of the (a) subject to paragraph (d), a revetment is suitably designed for its
revetment or seawall. or seawall provides for a sub-layer or purpose.
enough filter material to prevent
erosion of the land under the
revetment or seawall;
(b) subject to paragraph (d), the bottom
edge of the base of a revetment or
seawall will withstand undermining by
scour;
c) subject to paragraph (d), AS 2758 to
the extent requirements stated in the
Standard apply to the sizing and
grading of filter layers and armour
materials;
d) if a relevant planning scheme standard
is more stringent than the standard in
paragraph (a), (b) or (c) – the relevant
planning scheme standard, to the
extent it is more stringent than the
standard in paragraph (a), (b) or (c).
19.4 Prescribed tidal works The design and construction of the Compliant
that are a revetment or revetment or seawall is consistent with the
seawall are not adversely following standards:- The engineer’s certificate
affected by hydrostatic a) subject to paragraph (b), AS 4678 to attached to the application
pressure. the extend requirements stated in the confirms the design is in
Standard apply to hydrostatic pressure accordance with the relevant
for earth-retaining structures; standards.
b) if a relevant planning scheme standard
is more stringent than the standard in
paragraph (a) – the relevant planning
scheme standard, to the extent it is more
stringent than the standard in paragraph
(a).
Performance Criteria Acceptable Solution Comments
Design, construction and safety – wharves
20.1 Prescribed tidal works The design and construction of the wharf is Not applicable.
that are a wharf are designed consistent with the following standards:-
and constructed in a way to a) subject to paragraph (b):- The proposal is not a wharf.
ensure it is able to support its i) for a wharf constructed within a
intended loads, having regard marina – AS 3962 to the extent
to its relevant loading requirements stated in the
matters. Standard apply to relevant loading
matters for the design or
construction of the wharf; or
Development Assessment Report Page 36 of 42
Operational Works
37 Mossman Court, Noosa Heads 4567
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.