Environmental Management Plan
Peregian Beach Caravan Park
CONSTRUCTION PHASE - EROSION & SEDIMENT CONTROL
Inspection of performance of the geo-log and diversion banks during a significant stormwater event (water effectively diverted to
grassed areas, low turbidity of diverted water, no erosion under the geo-log):
Site entry and exit points
- Daily inspection of the road surface beside the exit for sediment movement off the site:
Designated on-site stockpiles
Daily inspection of geo-log and sediment fence for structural integrity;
Daily inspection of the sediment fence for sediment accumulation; and
Daily inspection of stockpile for effective cover, or wetness and erosion if cover has been removed.
Downslope sediment controls
Inspection for rills immediately after rainfall events;
Daily inspection of sediment fences for structural integrity and sediment accumulation (build up behind sediment fences should
be no more than 1/3 of the fence height) weekly and immediately after a rainfall event; and
Measure suspended solids of stormwater flowing into and out of the building site during stormwater events (suspended solids in
overtopped stormwater entering the terminal wetland should not be excessively high when compared with suspended solids
entering the construction site).
Maintaining groundcover
Daily inspection of temporarily disturbed ground to ensure these areas are covered with erosion mats;
Daily inspection of bare ground to ensure reseeding and irrigation is occurring;
Inspection for rills after stormwater events; and
Measure suspended solids of stormwater flowing into and out of the building site during stormwater events (suspended solids in
water existing the site should not be excessively higher than water entering the site).
Reporting i Responsibility Reporting
n Daily inspection checklist to be completed by Construction Foreman;
• Monthly reporting by the Construction Foreman to Site Manager addressing the monitoring results during construction, including:
1 1 0 1 14_PR20517_EMP.doc Page I S
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.