Environmental Management Plan
Peregian Beach Caravan Park
CONSTRUCTION PHASE - EROSION & SEDIMENT CONTROL
Improve delivery of high pressure water hose if possible; and
Avoid work under muddy conditions.
Designated on-site stockpiles
• When loss of materials from stockpiles is occurring:
Follow contingency plan as outlined for EP-SECP-03 in the Stormwater Management Plan / Sediment and Erosion Control Plan;
Repair the geo-log, perimeter stockpile covers and sediment fence, if required:
Address upslope controls if required (refer to'Upslope stormwater flow diversion); and
Contractor to reinforce the need to cover stockpiles.
Downslope sediment controls
n When significant loss of sediment down-slope is occurring:
Follow contingency plan as outlined for EP-SECP-04 in the Stormwater Management Plan / Sediment and Erosion Control Plan;
Improve groundcover if rills are evident;
Repair sediment fences;
Remove sediment from sediment fences and stockpile (refer to 'Designated on-site stockpiles) for later use as topsoil; and
Install temporary downpipes promptly.
Maintaining groundcover
n When water is flowing over unstable ground:
- Follow contingency plan as outlined for EP-SECP-05 in the Stormwater Management Plan / Sediment and Erosion Control Plan;
Building contractor to reinforce the need for managing off site movement of disturbed soil because of the high environmental
values associated with Noosa National Park;
- Ensure that erosion mats are intact and properly installed: and
Ensure that re-seeding and irrigation is occurring. Install additional erosion mats, grass cover, or turf if necessary.
110114_PR20517_EMP.doc Page 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.