Environmental Management Plan
Peregian Beach Caravan Park
CONSTRUCTION PHASE - SURFACE & GROUND WATER QUALITY
This element to be read in conjunction with the Stormwater Management Plan & Sediment/ Erosion Control Plan (Simmonds & Bristow, 2010) (Appendix A) and the Erosion
and Sediment Control Element (Section 3.1).
Performance Criteria n Performance requirements for water discharge(s) during construction of the site include (in accordance with the
construction phase objectives in the Noosa River: Environmental Values and Water Quality Objectives 2007 and
Queensland Water Quality Guidelines 2009):
Total suspended solids <50 mg/L and/or 80% reduction in suspended solids compared to untreated stormwater
runoff from the developed part of the site;
60% reduction in Total Phosphorus compared to untreated stormwater runoff from the developed part of the site;
45% reduction in Total Nitrogen compared to untreated stormwater runoff from the developed part of the site;
pH 6.5 - 8.5; and
Turbidity: Discharge <50NTU and/or released waters from approved discharge point/s have turbidity less than 10%
above that of receiving waters (measured immediately upstream of the site).
n No exposure of acid sulfate soils (ASS) to the external environment;
n Correct management of acid sulfate soils if exposure occurs;
• No discharge of contaminated water to receiving waters;
n No deterioration in water quality in adjacent surface waters; and
• No deterioration in groundwater quality.
Implementation Strategies n Implement all erosion and sediment temporary control measures (as outlined in the Soil Erosion and Sediment Control
element of this EMP; Section 3.1, and the Stormwater Management Plan / Sediment and Erosion Control Plan Appendix
A) prior to the commencement of bulk earthworks;
n Implement all Hazardous Substances and Waste Management implementation strategies (as outlined in the EMP;
Section 3.3 & Section 3.10);
n All contractors are to be trained during site inductions on the identification of Potential Acid Sulfate Soils (PASS) and ASS.
Common indicators of PASS or ASS include:
110114_PR20517-EMP.doc Page 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.