Environmental Management Plan
Peregian Beach Caravan Park
CONSTRUCTION PHASE - SURFACE & GROUND WATER QUALITY
Monthly audit to be completed by Environmental Officer, and should include any recommended corrective action and
document any information provided by the contractor;
n Monthly water quality monitoring to be completed by Environmental Officer.
n In the event of non-conformance, the Site Manager is to report to the Environmental Officer. The Environmental Officer
shall inspect and record:
Nature of the non-conformance:
Actions taken to prevent the non-conformance from recurring;
Provide photographic evidence of completed remedial actions; and
Provide laboratory analysis of sampling locations.
• In the event of material, or serious environmental harm, the Site Manager is to report to Council and appropriate regulatory
authorities.
Responsibility
• Construction Foreman;
• Site Manager; and
• Environmental Officer.
Corrective Action n Corrective action will be undertaken by the Construction Foreman;
• In the event of serious environmental harm, consultation will be undertaken with Council and regulatory authorities for an
agreement to be reached in relation to appropriate corrective and preventative actions to be taken;
• In the event of exposure of release of PASS or ASS, consultation will be undertaken with an appropriately qualified
professional and agreement reached in relation to appropriate corrective and preventative actions to be taken;
• Corrective actions outlined in the Stormwater Management Plan / Sediment and Erosion Control Plan (Appendix A)
including those outlined in Section 3.1 of this EMP.
1101 14_PR20517_EMP.doc Page 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.