Environmental Management Plan
up, Peregian Beach Caravan Park
DESIGN / CONSTRUCTION PHASE - HAZARDOUS SUBSTANCES
Performance Criteria Hazardous substances from the construction site are properly managed and do not pollute surface water runoff and
adjacent wetlands;
• No uncontrolled spills of oils, fuels and chemicals to the external environment;
n Storage of all hazardous materials complies with the requirements of relevant legislation, Australian Standards and/or
Codes of Practice, including Environmental Protection (Waste Management) Policy 2000, Dangerous Goods Safety
Management Act 2001, AS 1940: 2004 The storage and handling of flammable and combustible liquids, Workplace Health
and Safety Act 1995 and Carriage of Dangerous Goods by Road Act 1984; and
n Clean-up equipment and materials made available on-site at all times.
Implementation Strategies Handing and Storage
n The storage of flammable and combustible liquids will be in accordance with Australian Standard (AS)1940-2004;
• A copy of Material Safety Data Sheets (MSDS's) to be provided and made readily available to construction Contractors for
all hazardous and/or potentially polluting material;
n Any spill must be cleaned up in accordance with the MSDS's and the Environmental Emergency Response Plan:
n All employees and subcontractors will be trained on the handling and use of hazardous substances as part of the site
induction process;
n Transport, use and storage of hazardous materials on the Project shall be in accordance with the requirements of:
the relevant MSDS's;
Part 37 "Hazardous Substances" of the Workplace Health and Safety Regulation 1997;
the Code of Practice "The Management of Hazardous Substances at Work";
the Dangerous Goods Safety Management Act 2001 and Dangerous Goods Safety Management Regulation 2001;
AS 1940-2004 The Storage and Handling of Flammable and Combustible Liquids.
• Retain only minimal required quantities of chemicals, fuels, oils, etc on site during construction at any particular time;
• Arrange for delivery of products on an 'as required' basis;
• No permanent storage of potential contaminants on site;
• Chemicals, fuels, oils, etc shall be stored within an impervious bunded area or compound in accordance with the Australian
Standards and/or Codes of Practice and will be located at least 50 m from waterbodies;
n Suitable quantity of absorbent material (e.g. Enretech) is to be available near storage areas in case of a spill;
1 101 14_PR20517_EMP.doc Page 23
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.