Environmental Management Plan
Peregian Beach Caravan Park
DESIGN / CONSTRUCTION PHASE - HAZARDOUS SUBSTANCES
Weekly records of visual inspections by Construction Foreman;
• Monthly reporting by the Construction Foreman to Site Manager covering all monitoring activities and results as well as
compliance with performance criteria;
n Monthly audit report to be completed by Environmental Officer and should include any recommended corrective action and
document any information provided by the Construction Foreman;
n Non-conformance and complaint details will be forwarded to the Site Manager as soon as practicable;
• All complaints or incidents of non-compliance are to be recorded on the site Incidents and Complaints Register (refer to
Section 2.5);
n In the event of a spill the following additional details are to be recorded in the Incidents and Complaints Register:
Reasons why the spill occurred;
Quantity and type of oil/chemical spilled;
Actions implemented to clean up the spill;
Method of disposal of used absorbent and spilled petroleum product;
Details of any potential or actual environmental harm caused consequent to the spill; and
Cost to clean up spill (all costs of materials and labour).
• The Site Manager is to report any events of non-conformance to the Environmental Officer;
n In the event of material or serious environmental harm, the Site Manager is to report to Council and appropriate regulatory
authorities;
Responsibility
• The Construction Foreman
n Site Manager
n Environmental Officer
n Steps to be implemented if a spill occurs:
Corrective Action
stop the spillage or leakage at the source;
ensure the spill does not leave the site, enter waterbodies or drains by bunding (e.g. earth mound, filter sock,
Enretech);
chemical spills to be cleaned up in accordance with the relevant Material Safety Data Sheet for the product spilled;
Use absorbent materials (e.g. Enretech (land spills) or Cellusorb (water spills) to isolate and clean up the spills;
1101 14_PR20517_EMP.doc Page 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.