                                                                                                                                 Environmental Management Plan
                                                                                                                                    Peregian Beach Caravan Park




                                        -    Transport to alternative site for breaking down materials provided that all necessary permits have been obtained
                                             to allow the alternate site to be used for this purpose; and
                             Rehabilitation Works
                             n Wire fauna fence is to be erected around the parkland boundary to prevent any unauthorised access to the area during
                                 construction;
                             n   Construction workers are to be specifically advised of the restrictions applying to the rehabilitation areas;
                             n   All erosion and sediment control devices are to be in place to prevent damage to the parkland area;
                             n   Weed management is to be implemented on the site in accordance with the methods outlined in the Ecological Restoration
                                 Plan (Appendix B) (refer to the Weed and Pest Control element of this EMP; Section 3.5); and
                             n   Implementation of any other control measures nominated in the Ecological Restoration Plan (Appendix B).
Monitoring                   n   Daily inspection of retained vegetation areas by the Construction Foreman to ensure fencing and signage is in place, mulch
                                 levels are correct within the TPZ and retained vegetation is not damaged;
                             n   Daily monitoring of clearing techniques by a qualified Arborist to ensure there are no non-conformances;
                             n   A qualified Arborist shall monitor the health and structural integrity of the trees and vegetation to be retained. This
                                 monitoring shall occur at least monthly during the construction period;
                             n   Wire fencing around the parkland area is to be inspected regularly to ensure it remains properly installed; and
                             n   All weed removal activities have been undertaken.
Reporting / Responsibility   Reporting
                             n Monthly reporting by the Construction Foreman to Site Manager of:
                                             All monitoring and inspection activities;
                                             Implementation strategies and compliance with performance criteria; and
                                             Corrective action undertaken.
                             n   Copies of the report to be provided to Sunshine Coast Regional Council if requested:
                             n   Any incidents of non-compliance to be recorded in the Incidents and Complaints Register (Section 2.5);
                             n   The Construction Foreman to immediately notify the Site Manager of any unauthorised damage to retained vegetation on
                                 the site who is then to notify the Site Aborist and Environmental Officer;
                             n   Council to be notified of the non-compliance incident, where appropriate; and
                             n   Site Arborist is to provide a report detailing clearing works and health of retained trees post clearing works, where required.



1101 14_PR20517_EMP.doc                                                                                                                      Page 29

Used in these records

About this file

File size
49.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application Part 2 - Environmental & Stormwater Management Plans.pdf · 49.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.