Environmental Management Plan
Peregian Beach Caravan Park
DESIGN / CONSTRUCTION PHASE - AIR QUALITY
Dust
n Completion of tree and vegetation clearing in stages, in an order that minimises the area exposed at any one time:
• Clear only the minimum area required in accordance with the Arborist Report (Appendix C) (refer to the Vegetation Protection Element,
Section 3.4);
• Exposed soil / disturbed areas are to be stabilised as soon as possible after the disturbance using mulch or other suitable covers;
n Rehabilitation/landscaping of disturbed area, as soon as practical;
• Covering of loads entering and leaving the site;
• Collection of material on sealed public roads which falls from trucks or their wheels by sweeping on a regular basis;
• Use of recycled water trucks or other dust suppressants to work areas and haul routes on an as required basis to prevent dust nuisance;
n All recycled water to be obtained from Council designated points;
n Limit the amount and extent of stockpiling;
n Stabilisation of stockpile areas to occur immediately. Stockpiles of finer materials to be covered with denser material resistant to wind blow
(e.g. clay soil or covered with tarps) or use of some other stabilisation process (e.g. spray on binders, hydromulch, etc):
n A speed limit of 30 km/hr shall apply to all vehicles on the site;
• Shaker grids to be installed at access points and access tracks to be armoured where required to remove mud and sand from haul trucks
leaving the site; and
• Wind break screens shall be employed where considered necessary between working areas and abutting vegetation and development.
Monitoring • Daily site inspections by the Construction Foreman of the:
Types;
Locations; and
Details of control measures in place.
n Weekly monitoring by the Construction Foreman on the effectiveness of control measures in place by assessing against the Performance
Objectives/indicators for this element:
n If requested by Council in response to a complaint of nuisance, air quality monitoring shall be undertaken by a suitably qualified consultant
in accordance with DERM's Air Quality Sampling Manual (1997); and
n Monthly audit and review of control measures implemented on site by the Environmental Officer.
Reporting / Responsibility Reporting
n Construction Foreman to maintain regular records of meteorological conditions, i.e. wind speed, direction and rainfall (records to be obtained
1101 14-PR20517-EMP.doc Page 40
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.