Environmental Management Plan
Peregian Beach Caravan Park
Performance Criteria To ensure wastes from the construction site are properly managed and do not pollute any waterways / wetlands;
No uncontrolled waste or litter to be observed on the construction site or access roads;
Wastes are properly disposed of without harm to the surrounding environment; and
Compliance with Environmental Protection (Waste Management) Policy 2000.
Implementation Strategies • Waste management practices on the site should adopt the waste management hierarchy and principles as prescribed in the
Environmental Protection (Waste Management) Policy 2000. Opportunities to avoid, reduce, reuse and recycle waste
materials are to be investigated;
n Provide industrial waste disposal bins for disposal of general inert construction wastes. Separate disposal bins clearly
marked are to be provided for recyclables;
n All wastes shall be securely stored and protected from rain and stormwater contact;
• Construction waste is to be regularly collected. Construction waste awaiting collection is to be appropriately contained on
site in a tidy manner and does not have the potential to be wind blown;
n Prohibit the discard of cigarette butts to ground. The Construction Foreman is to address the management of cigarette butts
on site and inform all contractors of the correct procedures;
n Washouts of concrete trucks shall not be permitted on site;
n Wheelbarrows and other mortar/concrete receptacles shall be cleaned out in bunded wash area for larger items and a
sealed wash drum system for small items. All waste materials shall be collected for disposal;
• Cleared native vegetation to be processed and transported off site to be reused for mulch, firewood, etc;
• Locate and manage construction storage areas so that there is no impact following completion of works;
• Only minor servicing of vehicles shall take place (e.g. replace burst hydraulic hoses). All other servicing shall be
undertaken off site;
• Store petroleum products in a secure, bunded compound. Refer to the Hazardous Substances Element (Section 3.3);
• Retain only minimal required quantities of chemicals, fuels, oils etc on site during construction at any particular time. These
products shall be stored within a bund (AS1940) with a suitable quantity of absorbent material (e.g. Enretech) available on
site in case of a spill. Refer to the Hazardous Substances Element (Section 3.3);
n All general construction waste shall be removed from the site and disposed of at a waste disposal facility licensed to
receive such wastes at the completion of construction works;
1101 14_PR20517_EMP.doc Page 4S
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.