                                                                                                                                             Environmental Management Plan
                                                                                                                                                 Peregian Beach Caravan Park




                                 -    Report results of water quality testing against the water quality targets annually to senior management:
                           Responsibility
                                      Landscape contractor and On-Site Manager/Owner (buffers, bioretention trenches);
                                      Plumbing subcontractor and Site Manager (pipe infrastructure); and
                                     Suitably qualified environmental consultant (all water quality & soil monitoring activities).
Corrective Action          Maintaining the vegetated buffer zones
                           n  When loss of control of the landscape irrigation system and vegetation buffer occurs:
                                      Follow contingency plan as outlined for EP-SMP-03 in the Stormwater Management Plan / Sediment and Erosion Control Plan;
                                     Site Manager to reinforce the need for off site disposal of composting;
                                     Site manager to reinforce the need to avoid leaching of fertiliser nutrients into stormwater;
                           Maintaining bioretention trenches
                           n   When loss of control of stormwater flow through the bioretention trench occurs:
                                      Follow contingency plan as outlined for EP-SMP-05;
                                      Remove litter, accumulated sediment, silt drapes (by rake and spade) from trench;
                                      Remove detritus from outlet weir grate;
                                      Restore vegetation if required by transplanting bare patches;
                                      Remove weeds manually;
                           Maintaining pipe Infrastructure
                           •   When loss of control of stormwater flow through the pipes occurs:
                                      Follow contingency plan as outlined for EP-SMP-06;
                                      Remove visible blockages to inflow pipes after flows have ceased:
                                      Call plumbing subcontractor to inspect pipes for blockages and leaks as required;
                           Maintaining the constructed wetland system
                           n   When poor quality water flows through the gabion wall:
                                      Follow contingency plan as outlined for EP-SMP-07;
                                      Manually remove accumulated litter and weeds;
                                      Restore locally native plant species if required;
                                      Identify upstream controls causing poor water quality and initiate improvements; and



1 101 I4_PR20517_EMP.doc                                                                                                                                Page 52

Used in these records

About this file

File size
49.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application Part 2 - Environmental & Stormwater Management Plans.pdf · 49.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.