                                                                                                                                                     Environmental Management Plan
                                                                                                                                                        Peregian Beach Caravan Park



OPERATIONAL PHASE - WATER CONSERVATION

                                           Ensure that the programmable logic delivers 2 - 5 mm/day onto the gardens; and
                                          Advertise that water used for irrigation is harvested and not from the mains supply.
Monitoring                   n      Monitoring recommended in the Stormwater Management Plan / Sediment and Erosion Control Plan (Appendix A), including:
                                 Maintaining 3m3 rainwater tank volume associated with each beach shack
                                           Annual inspection of the structural integrity of tanks (e.g. leaves and detritus, cracks, rust, leaks in guttering, roof, down-pipe and
                                          tank; check the mesh on the rainwater tank is intact and free of detritus);
                                           Monthly water quality monitoring(as outlined in Section 4.1);
                             Maintaining underground rainwater tanks associated with the ornamental garden irrigation scheme
                                           Daily inspection of the contributing catchment condition (hard surfaces used for collecting rainwater for pollutants such as oil or petrol
                                           spills, dirt, litter);
                                           Monthly inspection of the screen for litter and structural integrity;
                                           Annual inspection of the structural integrity of the tanks (cracks, cement rot, leaks, check inside the tanks for accumulated sediment
                                           and nuisance biota); and
                                           Monthly water quality monitoring (microbial, nuisance organisms, aesthetics, clarity and colour, toxic chemicals, oils and debris, as
                                           outlined in Section 4.1).
                             Irrigating the ornamental gardens
                                           Weekly inspection to ensure the 100m3 tanks do not overflow; and
                                           Monitoring of pipe infrastructure (daily inspection for evidence of leaking pipe-work; inspection of flow along pipe-work (entry and exit
                                           of water along pipework) during stormwater flow events).
Reporting / Responsibility   Reporting
                             •      Annual reporting of the rainwater systems and water quality performance (as outlined in Section 4.1), and exception reporting of failure and
                                    replacement, supplied to senior management;
                             Responsibility
                             •      Site Manager; and
                             n      Site Manager and plumbing subcontractor (underground rainwater tanks).
Corrective Action            Maintaining 3m3 rainwater tank volume associated with each beach shack
                             n      Correct structural integrity as required (e.g. clean out or repair guttering and downpipe, clean, repair or replace first flush diverter and mesh
                                    on rainwater tank if required);



1 101 14_PR20S 17_EMP.doc                                                                                                                                        Page 55

Used in these records

About this file

File size
49.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application Part 2 - Environmental & Stormwater Management Plans.pdf · 49.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.