Council archive · source document
Development Application Part 2 - Environmental & Stormwater Management Plans · OPW11/0335
Plans and drawings: the text below has words only, no drawings.
Very large file (49.6 MB): may take a few minutes to open.
Environmental Management Plan
FolVa-liq'
Peregian Beach Caravan Park
Table 1.1: Summary of Statutory Obligations
RELEVANT STATUTORY DOCUMENT
Federal
Environmental Protection and Biodiversity Conservation Development activities are not to pose a likely risk of
Act 1999 (EPBC Act) significantly impacting on Matter of National Environmental
Significance (MNES). The Noosa National Park adjacent
to the site is listed as a National Heritage Place and
contains known habitat for threatened species, which are
considered under the Act of MNES.
Australian Heritage Council Act 2003 Development activities are not to have an adverse impact
on cultural heritage areas. The Noosa National Park
adjacent to the site is listed on the Register of National
Estates database.
State
Aboriginal Cultural Heritage Act 2003 The Contractor is to comply with the Aboriginal cultural
heritage duty of care during construction and operational
phases.
Coastal Protection and Management Act 1995 Development activities must maintain, protect and
enhance the current extent and diversity of mapped
wetlands within and adjacent to the site. In particular,
development activities must maintain and enhance
environmental values and water quality, including
groundwater hydrology of receiving wetlands.
Environmental Protection Act 1994 The Contractor must uphold the duty of care as defined
under the Act:
A person must not carry out any activity that causes, or is
likely to cause, environmental harm unless the person
takes all reasonable and practicable measures to prevent
or minimise the harm"
Environmental Protection Policies for Air, Noise and Water The Contractor must take reasonable steps to ensure the
environmental values and quality objectives stated under
the relevant policies for the receiving environment are
achieved.
Land Protection (Pest and Stock Route Management) Act The Contractor must take reasonable steps to remove and
2002(LPA) maintain the site free of Class 1 and 2 species declared
under the LPA.
Nature Conservation Act 1992 (NCA) Development activities are to comply with the Act's
management intent for listed threatened species and
declared protected areas by ensuring minimal impact.
Construction and operational works are to be undertaken
1101 14 PR20517 EMP.doc Page 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.