Appendix D_Engineering Report

Attached to the e-mail MCU15/0109 IDAS Forms, Planning Report & Engineering Report - Links Drive Noosa Heads.

of 80

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (10.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 40, section 1. The text section number identifies this passage in the reader.

                                                     c)    ensuring stock piling, storage and vehicle
                                                     parking occur outside the areas of vegetation to
                                                     be retained;
                                                     AND
                                                     S25.5 Low impact construction techniques are RO25.3 Acknowledged.
                                                     used around areas of vegetation to be retained
                                                     to minimise interference with the vegetation.
O26                                                No solution provided                               RO26 Not applicable.
Roads and stormwater drainage infrastructure is
proven to be suitable for its use prior to Council
accepting the dedicated asset.

O27                                                   S27.1 The location, design and construction of RO27 Acknowledged.
Alignment of stormwater drainage infrastructure is to stormwater drainage structures is in accordance
allow for easy access for the ongoing maintenance by with Sections 4 and 5 of PSP5, Engineering
Council.                                              Design Standards - Roads, Drainage and
                                                      Earthworks;
                                                      AND
                                                      S27.2 Where infrastructure is located on private
                                                      land an easement is dedicated over the
                                                      infrastructure in accordance with Section 4 of
                                                      PSP 5, Engineering Design Standards – Roads,
                                                      Drainage and Earthworks.
O28                                                     S28.1 The following infrastructure components RO28 The existing road frontage is complete with
Development is provided with external roadworks already exist at the frontage of the site or are             kerb and channel and underground utilities.
along the full extent of the frontage of the site to an provided at the developer’s                          Any works within the road verge fronting the
appropriate standard having regard to the specified expense—                                                 site will be in line with Noosa Council
function of the road.                                   a)     full width sealed road;                       Standards.
                                                   b)   concrete kerb and channel where appropriate;
                                                        c)     forming and grading to footpaths;
                                                        d)     vehicular kerb and footpath crossings;
                                                        e)     a constructed bikeway;
                                                        f)     a constructed footpath;
                                                        g)     a constructed carriageway;
                                                        h)     required alterations to public utility mains,
                                                        services or installations;
Log in to download the original file

Appendix D_Engineering Report.pdf · 10.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.