The equipment required to undertake this work comprises an excavator mounted continuous flight
auger, a static pump and standard 5 tonne excavator. Concrete will be supplied by Mini-Mix trucks
i which will deliver concrete via the new crossover on Park Road.
The approximate volume of material to be removed is 400 cubic metres. This is equivalent to 100
i vehicles movements over the construction period. During loading, the vehicles will be required to
reverse onto the new driveway. There will be no loading of material on Park Road itself.
ij There are approximately 100 bored piers required for the contiguous piled wall. Based on an average 7
piles per day, the piling works should be completed comfortably Within 3 working weeks.
i The overall construction period for the basement garage is estimated to be six weeks.
1.3 Earthworks
i The earthworks on this project comprise bulk excavation and shoring for the garage and construction of
a new driveway and crossover on to Park Road. Material removed from site will be taken to a stockpile
i at Noosa landscape supplies, only one truck will be allowed to sit on the site at a time, subsequent
trucks will be driving to and from the stock pile. No materials will be left on the road reserve
; 1.4 Traffic Management
The first operation will be the construction of the basement car park. During this stage the builder shall
j engage the services of a traffic management company to ensure that there is no interference to the
general traffic using Park Road. Traffic controllers will be required to be present to direct vehicles during
the excavation and construction of the garage.
i When the garage has been completed, the new driveway and cross over and service connections will be
constructed. This will provide safe access for material deliveries form Park Road. Traffic controllers will
i direct major deliveries and departures from Park Road. The timing of deliveries shall be such that they
do not coincide with peak usage times in Park Road.
j Once the garage is completed. One of the two parking spaces will be used to provide secure storage and
the second space will accommodate a skip for rubbish removal.
1.5 Foundation Construction
i It is proposed to construct retaining walls to stabilize the dune area above the garage. The stability of
the dune slope above the piling rig would remain undisturbed during the piling process.
i It is proposed to install the steel screw piles using a 5 tonne tracked excavator. This machine will be
delivered to Park Road winched up to the building area.
i The site will be clearly pegged and fenced to ensure that the work area of the excavator is restricted to
the area of the proposed dwelling.See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001A7F25.001.pdfRelated documentPublic source context ↗
09/0578 - Operational Works - Landscaping, Carparking, Access, Frontage Works, Stormwater Drainage, Site Civil Works, Sewer & Water Reticulation [As Published]Related documentApplication case desk ↗
About this file
- File size
- 6.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.