3.5 WATER
3.5.1 Existing Infrastructure
The Unity Water As-Constructed Plans of the surrounding area indicate the following existing water reticulation information:
− An existing 180mm dia. water main is located below the eastern verge of the private access roadway along the full
length of the development site frontage; and
− An existing 150mm dia. property connection runs below the private access roadway from the eastern verge to the
western verge, to provide water service to the Lot 3 frontage.
The Unity Water As-Constructed Plans of the existing water infrastructure can be found in Appendix C of this report.
3.5.2 Proposed Infrastructure
The proposed water infrastructure for this development is as follows:
− A new property connection from the existing 180mm water main to service the Lot 7 development;
− Use the existing 150mm property connection below the western verge of the private access road to service the Lot
3 development; and
− As the surrounding roadways and services have been master-planned to service a fully developed catchment, it is
expected the existing water infrastructure has sufficient capacity to service the proposed development.
Refer to Appendix B for preliminary drawings of the proposed water works.
3.6 ELECTRICITY
The Energex Asset Plans from a Before You Dig investigation of the surrounding area indicate the following:
− Underground electrical infrastructure exists along private access roadway and surrounding road network; and
− It is expected this infrastructure can service the proposed development.
Energex Asset Plans of the existing electrical infrastructure can be found in Appendix C of this report.
Electrical services required for the proposed development including assessment of the existing infrastructure capacity will
be designed and determined by an electrical engineer and will be assessed by Energex during the detailed design phase of
the development.
3.7 COMMUNICATIONS
The Telstra Asset Plans from a Before You Dig investigation of the surrounding area indicate the following:
− Underground communications infrastructure exists along private access roadway and surrounding roadways; and
− It is expected this infrastructure can service the proposed development.
Telstra Asset Plans of the existing communications infrastructure can be found in Appendix C of this report. All works required
to provide communication services to the proposed development will be undertaken with the relevant service providers
approval and coordination.
www.bornhorstward.com.au Page 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 5 - Servicability Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 21.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.